Version 130 (modified by 14 years ago) (diff) | ,
---|
- Cluster D Integration
Cluster D Integration
1. Projects
ORCA/BEN (1582) and ORCA Augmentation (1700)
DOME (1599)
ViSE (1602)
Embedded Real-Time Measurements (ERM, 1631)
KanseiGenie (KanseiGenie, 1633)
Data Intensive Cloud Control (DICLOUD, 1709)
OKGems: Cyber-Physical System (OKGEMS, 1716)
Integrated Measurement Framework (IMF, 1718)
iGENI Distributed Network Research Infrastructure (IGENI, 1719)
LEARN Network (LEARN, 1733)
BBN ORCA Xen Cluster
Process for updating Milestones, submitting QSRs
2. Meetings and Demos
Suggested mailing lists for Cluster D participants:
GENI mailing lists, including the dev, discuss and geni-announce lists, plus working groups that cover your interests.
mail to cluster-d@renci.org for PIs and senior personnel, including administrative cluster-wide issues. / subscribe / mailman archieve
mail to geni-orca-users@renci.org primarily for developers, including technical discussions about the implementation, etc. / subscribe / mailman archieve
ORCA-fest May 28, 2009, web site
Cluster D Conference Call on June 11, 2009
Cluster D Review Meeting July 2, 2009
"ORCA/BEN Integration Demo with Stitching of VLANs between BEN and NLR", July 7, 2009
"ORCA/BEN Integration Demo July 7, 2009, web site
Cluster D Meetings at GEC5 July 20 and 21, 2009
Cluster D conference call on October 29, 2009
Cluster D Meetings at GEC6 on Nov 16 and 17, 2009, Agenda and Notes
Cluster D conference call on January 27, 2010
Cluster D conference call on February 3, 2010
NDL conference call on February 3, 2010
Cluster D conference call on February 17, 2010
Cluster D conference call on March 3, 2010
Cluster D demos at GEC7 on March 16 and 17, 2010
Cluster D Meetings at GEC7 on March 16 and 17, 2010, Agenda and Notes
Workshop on Future Resource Representations in GENI, after GEC7 on March 18, 2010, Agenda and Notes
Cluster D conference call on April 9, 2010
Cluster D conference call on April 23, 2010
Cluster D conference call on May 21, 2010
Cluster D conference call on June 18, 2010
Cluster D conference call on July 2, 2010
Workshop on Future Resource Representations in GENI, before GEC8 on July 20, 2010, Agenda and Notes
Cluster D Meeting at GEC8 on July 20, 2010, Agenda and Notes
3. References and Documents
GENI - ORCA web site, including ORCA code and ticket system
Subscribe to Cluster D mailing list (cluster-d@renci.org), for PIs and senior personnel, to discuss administrative cluster-wide issues
Subscribe to Cluster D mailing list (geni-orca-users@renci.org), primarily for developers, to discuss technical issues about the implementation, etc.
Prototype DOME controller and handler modules for ORCA, 2009
Spiral 1 Plan Document, on 7/02/09
Spiral 2 Roadmap slides, with task ratings, on 7/21/09
Cluster D Roadmap Document, on 10/15/09
Cluster D Roadmap Drawings, on 10/15/09
GENI Cluster D Spiral 2 Connectivity Plan, on 10/15/09
4. Roadmap for Spiral 2
4.1 Goals
The following goals have been established by the GPO for Spiral 2.
Goal 1: Live experiments, the central goal of Spiral 2. Support significant numbers of research experiments in the end-to-end prototype systems. The GPO expects live experimentation to begin near the end of Spiral 1, which will intensify through Spiral 2 as we begin continuous operation of the prototype systems. This will begin to give us all substantial (early) operational experience, as these experiments will help us all understand the prototypes' strengths and weakness, which will drive our Spiral 3 goals.
Goal 2: Identity management
Goal 3: Improved integration of data & control planes, within clusters
Goal 4: Instrumentation
Goal 5: Interoperability, permitting clusters to access the widest number of aggregate
4.2 Key Dates
Begin 9/1/09 or 10/1/09, depending on the project
ORCA Rel 1.3 10/1/2009
GEC6 11/16/09
ORCA Rel 2.1 2/1/10
GEC7 3/16/10
ORCA Rel 2.2 6/1/10
GEC8 7/20/10
End 8/31/10 or 9/30/10, depending on the project
ORCA Rel 2.3 10/1/10
4.3 ORCA Software Releases
4.3.1 Roadmap
The ORCA software releases are currently scheduled for every 4 mo. , and include work done by both Solicitation 1 (1582) and Solicitation 2 (1700) ORCA projects.
ORCA Rel 1.3 10/1/2009
ORCA Rel 2.1 2/1/10
ORCA Rel 2.2 6/1/10
ORCA Rel 2.3 10/1/10
The following roadmap describes features and capabilities of ORCA software releases.
Figure 1-6: Slice controller API on the service manager
Figure 1-5: Identity provider verifies login
4.3.2 Status
1) For latest status, go to
GENI - ORCA, web site maintained by RENCI, including ORCA code and ticketing system
or contact Ilia Baldine Ilia Baldine at RENCI
4.3.3 Issues
1) Revoking / Canceling Leases
With ORCA, is there a method for leases to be canceled, or for outstanding requests to be revoked? This is required, or at least very highly desired, for DOME. Some scenarios:
- An experiment is started on the buses and the researcher
begins getting erroneous results, or the experiment
starts generating too much data (this happens). We'd like
to be able to prematurely terminate a lease to stop the
experiment, even if the allocated resources are not
returned to the pool.
- An experiment is scheduled for the future, but then the
researcher discovers he or she wants to change the
experiment or alter the time.
Obviously, there are many other scenarios that make the functionality desirable.
4.4 Cluster D Operating Capabilities and Clearinghouse
4.4.1 Roadmap
The following roadmap describes features and capabilities of the Cluster D operating environment, including a production-level Cluster D clearinghouse.
Figure 1-1: Cluster D Configuration at start of Spiral 2
Figure 1-2: Message flows between actors
Figure 1-3: Parallel local and clearinghouse brokers
Figure 1-4: Experiment from remote or local service manager, and clearnghouse broker
4.4.2 Status
For access to Cluster D Clearinghouse, go to Cluster D Clearinghouse at RENCI ; get login from Ilia Baldine
1) Clearinghouse at RENCI: Yes?
2a) BEN and VM brokers in clearinghouse: Yes?
2b) DOME broker in clearinghouse: Yes?
2c) ViSE broker in clearinghouse: Yes?
2d) Kansei broker in clearinghouse: Yes?
2e) BBN broker in clearinghouse: No?
Figure 1-1: Cluster D Configuration at start of Spiral 2
4.4.3 Issues
4.5 Cluster D VLAN Capabilities
4.5.1 Roadmap
The following roadmap describes Cluster D VLAN capabilities.
4.5.2 Status
1) "All S1 aggregates connect to Internet2 (or NLR) with link capable of Layer 2 connection" Due 10/1/09
1a) BEN and VMs connected to NLR; see BEN Connectivity
1b) DOME connected to Internet2, or NLR; see DOME Connectivity
1c) ViSE connected to Internet2, or NLR; see ViSE
1d) Kansei not connected?; see Kansei Connectivity
1e) BBN VMs connected to NLR?; see ?
2) "Cluster D completes plan for the setup of VLANs between testbeds, to be carried by Internet 2 (or NLR) backbone network between the testbeds" Due 11/16/09, GEC6
See: GENI Cluster D Spiral 2 Connectivity Plan
4.5.3 Issues
4.6 Cluster D Experiment Capabilities
4.6.1 Roadmap
The following roadmap describes Cluster D experiment capabilities.
Figure 1-3: Parallel local and clearinghouse brokers
Figure 1-4: Experiment from remote or local service manager, and clearnghouse broker
Figure 1-7: Experiment with two aggregates
4.6.2 Status
1) "All S1 aggregates ready for experiments by outside researchers" Due 10/1/09
1a) BEN experiments by ERM project?
1b) DOME experiments by Undergraduate networking class in fall 2009?
1c) ViSE experiments using rapidly deployable node?
1d) Kansei experiments by internal researchers?
1e) BBN VMs experiments by?
2) "All S1 aggregates ready for experiments by researchers using remote SMs and CH brokers." Due 11/16/09, GEC6
4.6.3 Issues
2a) For each S1 aggregate, how can remote portal and SM be built?
2b) DOME and Federated Scheduling, i.e., towards an experiment that utilizes resources from multiple testbeds
5. Cluster D Connectivity Plan
5.1 Control Framework Message Flows
Figure 1-1: Cluster D Configuration at start of Spiral 2
Figure 1-2: Message flows between actors
5.2 Component Programming via SSH
Figure 2-1: SSH Access to a Component
5.3 VLAN Connectivity Between Aggregates
5.4 VLAN Connectivity for GEC7 Demos
From 2/3 call:
+ Planning on a demo, RENCI, iGENI, UMass
+ Both first day, and plenary
+ BBN will map VLAN, from UMass to BBN, to NLR FrameNet (which now terminates at RENCI)
+ Overall path: from UMass, through NOX, to BBN, through NOX, through NLR Framenet, to iGENI, to RENCI.
+ To setup path: David Irwin (UMass Amherst), Chaos Golubitsky (BBN), Chris Heermann (RENCI), Jim Chen (Northwestern)
+ Chris Heermann (RENCI) coordinates
+ Pending: UMass direct connection to NLR FrameNet
+ Pending: BBN will get Cisco 3750, which can be used later
+ Pending: x2 NLR FrameNet ports for Starlight
Attachments (23)
- 070209b ClusterD_Spiral1_Plan.doc (90.0 KB) - added by 15 years ago.
- 072109b ClusterD_Meeting_GEC5.ppt (311.5 KB) - added by 15 years ago.
- 092309 ORCA_APIs_Flows.doc (11.8 MB) - added by 15 years ago.
- DOME-Federation.pdf (105.6 KB) - added by 15 years ago.
- 101509 ClusterD_Spiral2_Roadmap.pdf (133.5 KB) - added by 15 years ago.
- Visio-101509_ClusterD_Spiral2_Drawings.pdf (103.5 KB) - added by 15 years ago.
-
Visio-101509_ClusterD_Spiral2_Drawings_Page_01.2.jpg (495.5 KB) - added by 15 years ago.
fig 1-1
-
Visio-101509_ClusterD_Spiral2_Drawings_Page_02.jpg (389.9 KB) - added by 15 years ago.
fig 1-2
-
Visio-101509_ClusterD_Spiral2_Drawings_Page_03.jpg (280.4 KB) - added by 15 years ago.
fig 1-3
-
Visio-101509_ClusterD_Spiral2_Drawings_Page_04.jpg (272.6 KB) - added by 15 years ago.
fig 1-4
-
Visio-101509_ClusterD_Spiral2_Drawings_Page_05.jpg (292.0 KB) - added by 15 years ago.
fig 1-5
-
Visio-101509_ClusterD_Spiral2_Drawings_Page_06.jpg (290.3 KB) - added by 15 years ago.
fig 1-6
-
Visio-101509_ClusterD_Spiral2_Drawings_Page_07.jpg (299.1 KB) - added by 15 years ago.
fig 1-7
-
Visio-101509_ClusterD_Spiral2_Drawings_Page_08.jpg (491.8 KB) - added by 15 years ago.
fig 1-8
-
Visio-101509_ClusterD_Spiral2_Drawings_Page_09.jpg (300.9 KB) - added by 15 years ago.
fig 2-1
-
Visio-101509_ClusterD_Spiral2_Drawings_Page_10.jpg (304.6 KB) - added by 15 years ago.
fig 2-2
- features1.jpg (346.8 KB) - added by 15 years ago.
- features 2.jpg (235.1 KB) - added by 15 years ago.
- ops1.jpg (171.0 KB) - added by 15 years ago.
- ops2.jpg (71.3 KB) - added by 15 years ago.
- experiment.jpg (167.3 KB) - added by 15 years ago.
- vlan.jpg (156.1 KB) - added by 15 years ago.
- Visio-111609_ClusterD_Connectivity_Page_3.jpg (251.9 KB) - added by 15 years ago.