The SALT installation began today (9/2/09) and is expected to finish by Friday the 4th. John Graham at IU GlobalNOC will configure the I2 wave to directly connect the WASH and SALT sites, with testing available by early next week.
The SALT IP address assignments and wiring diagrams are available in ticket #173
Change History (2)
comment:1 Changed 15 years ago by
comment:2 Changed 15 years ago by
Resolution: | → fixed |
---|---|
Status: | new → closed |
This install was completed on September 4th.