Description
Second installation will be in Salt Lake City in early September. Must ship to Bloomington by 8/15.
Attachments (1)
Change History (9)
comment:1 Changed 15 years ago by
comment:2 follow-up: 3 Changed 15 years ago by
I2 has received the SPP hardware for SALT.
"Install in WASH has begun. It should be a 3 day install with all work completed by Wednesday
We have the SPP equipment for SALT and KANS."
comment:3 Changed 15 years ago by
"Install in WASH has begun. It should be a 3 day install with all work completed by Wednesday
Forgot to source. This was from Christopher Small at I2.
comment:4 Changed 15 years ago by
SALT install should be Sep. 2-4th according to Christopher Small at I2.
comment:7 Changed 15 years ago by
SPP SALT was able to talk to SPP WASH over the GENI wave via ProtoGENI's ProCurve.
Note: See
TracTickets for help on using
tickets.
Salt Lake city SPP node equipment received as reported by Chris Small at GRNOC on 8/3.
"We have received the SPP portion of the WASH node this afternoon and have the KANS SPP node
We should be on schedule for full install of the WASH node August 17-19 if we can get the ProtoGENI switch shipped this week. If we can get the ProtoGENI switch/servers for KANS the week of the August 17th we can get a full install in KANS.
We are planing on picking up the SALT ProtoGeni from U of Utah. We will need the SPP equipment shipped to arrive the week of Aug 17th we should be able to get it installed according to the schedule by the first week of September as well."