49 | | || 1 || Identify Outdoor Site on Campus || - || Completed || -|| Likely site is top of student housing building, on a hill.|| |
50 | | || 2 || Obtain FCC License || - || Completed || - || || |
51 | | || 3 || Identify Indoor Equipment Room on Campus || - || Completed || - || || |
52 | | || 4 || Install Wiring at Outdoor Site and to Indoor Equipment Room || - || Completed || - || || |
53 | | || 5 || Install Pole at Outdoor Site and Ground || - || Started || - || || |
54 | | || 6 || Install Antenna at Outdoor Site || - || Started|| - || || |
55 | | || 7 || Install Base Station Outdoor Unit || - || Started || - || || |
56 | | || 8 || Complete Wiring at Outdoor Site and to Indoor Equipment Room || - || Started || - || || |
57 | | || 9 || Install Indoor Equipment Racks and Ground || - || Started || - || || |
58 | | || 10 || Install 120VAC and -48VDC Power Feeds and/or Supplies || - || Started || - || || |
| 49 | || 1 || Identify Outdoor Site on Campus || - || Completed || -|| Identified 2 locations: 1 on the hill: Spraul Hall one of the student housing building; the second one on Boelter Hall CSD. Initial Setup on Boelter Hall for Testing purposes. The WiFi sites are 6 and they cover the whole campus; topology posted as picture below. || |
| 50 | || 2 || Obtain FCC License || - || Completed || - || 2 Year License Granted, Additional years if needed will be requested. The license has 2 frequencies 2,575MHz an 2,590MHz. 2 Campus Locations are authorized to transmit.|| |
| 51 | || 3 || Identify Indoor Equipment Room on Campus || - || Completed || - ||2 Locations 1 in Boelter Hall and 1 in Spraul Hall.|| |
| 52 | || 4 || Install Wiring at Outdoor Site and to Indoor Equipment Room || - || Started || - ||Indoor Completed. Outdoor completion expected on 9/20- pending Tower Arrival|| |
| 53 | || 5 || Install Pole at Outdoor Site and Ground || - || Started || - || Must is purchased, the 8' tall aluminum tower is ordered but not yet delivered.|| |
| 54 | || 6 || Install Antenna at Outdoor Site || - || Started|| - ||The Roof-Top metal Grid has been installed as well as the mounts. Waiting for tower to finalize. || |
| 55 | || 7 || Install Base Station Outdoor Unit || - || Started || - ||Infrastructure work done. Cable wiring on way. || |
| 56 | || 8 || Complete Wiring at Outdoor Site and to Indoor Equipment Room || - || Started || - ||Indoor is finalized, outdoor is on hold for missing parts expected anytime now. || |
| 57 | || 9 || Install Indoor Equipment Racks and Ground || - || Started || - ||Rack has not yet been received is expected in September.|| |
| 58 | || 10 || Install 120VAC and -48VDC Power Feeds and/or Supplies || - || Started || - ||We opted for bringing up the 40DC power, purchase of water proof cable and connectors has been made delivery is expected on 9/8/2010. || |