wiki:WIMXUCLA

Version 13 (modified by Giovanni Pau, 14 years ago) (diff)

--

Project Number

1797

Project Title

C-VeT --UCLA Campus Vehicular Testbed: An Open Platform for Vehicular Networking
a.k.a WIMXUCLA

Technical Contacts

PI: Mario Gerla gerla@cs.ucla.edu
Giovanni Pau Giovanni Pau

Participating Organizations

UCLA CS Dept, Los Angeles, CA

GPO Liaison System Engineer

Harry Mussman hmussman@geni.net

Scope

This project will add WiMax capability to a Campus Vehicular Testbed (C-VeT) to support the deployment and testing of vehicular services and applications over both WiFi and WiMax. It will feature resource virtualization in order to enable shared access by multiple experimenters using the ORBIT Management Framework (OMF). To establish the WiMax capability, we will procure a “GENI WiMax base station kit”.

Current Capabilities

Milestones

MilestoneDate(WIMXUCLA: S2.a Begin deployment of dual-mode vehicular nodes (WiFi and WiMax))?

Campus Installation Checklist

UCLA

Contact(s):
PI: Mario Gerla gerla@cs.ucla.edu
Giovanni Pau

Step Description Planned Started Completed Comment
1 Identify Outdoor Site on Campus - Completed - Identified 2 locations: 1 on the hill: Spraul Hall one of the student housing building; the second one on Boelter Hall CSD. Initial Setup on Boelter Hall for Testing purposes. The WiFi sites are 6 and they cover the whole campus; topology posted as picture below.
2 Obtain FCC License - Completed - 2 Year License Granted, Additional years if needed will be requested. The license has 2 frequencies 2,575MHz an 2,590MHz. 2 Campus Locations are authorized to transmit.
3 Identify Indoor Equipment Room on Campus - Completed - 2 Locations 1 in Boelter Hall and 1 in Spraul Hall.
4 Install Wiring at Outdoor Site and to Indoor Equipment Room - Started - Indoor Completed. Outdoor completion expected on 9/20- pending Tower Arrival
5 Install Pole at Outdoor Site and Ground - Started - Must is purchased, the 8' tall aluminum tower is ordered but not yet delivered.
6 Install Antenna at Outdoor Site - Started - The Roof-Top metal Grid has been installed as well as the mounts. Waiting for tower to finalize.
7 Install Base Station Outdoor Unit - Started - Infrastructure work done. Cable wiring on way.
8 Complete Wiring at Outdoor Site and to Indoor Equipment Room - Started - Indoor is finalized, outdoor is on hold for missing parts expected anytime now.
9 Install Indoor Equipment Racks and Ground - Started - Rack has not yet been received is expected in September.
10 Install 120VAC and -48VDC Power Feeds and/or Supplies - Started - We opted for bringing up the 40DC power, purchase of water proof cable and connectors has been made delivery is expected on 9/8/2010.
11 Install Base Station Indoor Unit - - -
12 Complete Wiring of Base Station Indoor Unit - - -
13 Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units - - -
14 Install Ethernet (VLAN) Switch, or Identify Existing Capacity - - -
15 Install Linux Server(s) and Software - Started - WiFi MESH control center and network management is up and runnng. OMF Server is up and running. OMF 5.3 is running a testing server.
16 Connect Backbone Network - - -
17 Provide Reference Client Platform - - -
18 Initial Check-Out of Campus WiMAX Testbed - - -