Version 84 (modified by 10 years ago) (diff) | ,
---|
New Site Stitching Confirmation Tests Status
This page captures the status for stitching sites. Tests are defined in the New Site Stitching Confirmation Tests page. For a full list of available site see the GENI Network Stitching sites page.
Site Status
Undergoing Confirmation Tests:
Completed Stitching Confirmation Tests successfully: (11 sites)
University of Illinois, MAX, NYSERNet, Stanford University, University of Missouri, University of Wisconsin
There are 6 additional sites that were validated as part of the initial GENI Network Stitching Validation that have no test details on this page:
GPO ExoGENI, GPO InstaGENI, University of Kentucky ProtoGENI, University of Utah Downtown Data Center InstaGENI, University of Utah InstaGENI, and University of Utah ProtoGENI.
Upcoming Confirmation Tests:
Status Legend
Overall Site Status may be one of the following:
- Pass - Site confirmation tests completed successfully and site is ready for Experimenters.
- Pass: most criteria - Site partially confirmed with documented exceptions.
- Blocked - Site confirmation tests blocked by tracked issue.
- In Progress - Site confirmation tests in progress.
Individual Stitching Confirmation Test Status may be one of the following:
- Color(green,Pass)? - Test completed and met all criteria
- Color(#98FB98,Pass: most criteria)? - Test completed and met most criteria with exceptions documented
- Color(red,Fail)? - Test failed.
- Color(orange,Blocked)? - Test blocked by ticketed issues.
- Color(#63B8FF,In Progress)? - Test in progress.
Test Detail List
GPO OpenGENI
Site Status: In Progress
Stitching Confirmation Tests Logs: here
Stitching Request RSpecs: here
Test | State | Date Completed | Tickets | Notes |
OG-ST-1 New Site to GPO IG | Color(green,Pass)? | 2014-09-10 | No VLAN for co-located GPO IG, used Stanford IG as remote | |
OG-ST-2 Loop topology | Color(green,Pass)? | 2014-09-10 | ||
OG-ST-3 Linear topology | Color(green,Pass)? | 2014-09-11 | ||
OG-ST-4 New Site to GPO EG | N/A | No VLAN for co-located GPO EG, No other EG site support stitching | ||
OG-ST-5 Site Information | ||||
OG-ST-6 OpenFlow topology | Over ION |
MAX
Site Status: In Progress
Stitching Confirmation Tests Logs: here
Stitching Request RSpecs: here
Test | State | Date Completed | Tickets | Notes |
IG-ST-1 New Site to GPO IG | Color(green,Pass)? | 2013-12-03 | #1157 | |
IG-ST-2 Loop topology | Color(green,Pass)? | 2013-12-03 | ||
IG-ST-3 Linear topology | Color(green,Pass)? | 2013-12-03 | ||
IG-ST-4 New Site to GPO EG | Color(green,Pass)? | 2013-12-05 | ||
IG-ST-5 Site Information | Color(green,Pass)? | 2013-12-09 | ||
IG-ST-6 OpenFlow topology | Color(green,Pass)? | 2013-07-29 | over ION |
NYSERNet
Site Status: Pass
Stitching Confirmation Tests Logs: here
Stitching Request RSpecs: here
Test | State | Date Completed | Tickets | Notes |
IG-ST-1 New Site to GPO IG | Color(green,Pass)? | 2013-11-19 | ||
IG-ST-2 Loop topology | Color(green,Pass)? | 2013-11-19 | ||
IG-ST-3 Linear topology | Color(green,Pass)? | 2013-11-20 | ||
IG-ST-4 New Site to GPO EG | Color(green,Pass)? | 2013-11-19 | ||
IG-ST-5 Site Information | Color(green,Pass)? | 2013-11-20 | #1154 | |
IG-ST-6 OpenFlow topology | Color(green,Pass)? | 2013-07-29 | over ION |
Rutgers University
Site Status:
Stitching Confirmation Tests Logs: here
Stitching Request RSpecs: here
Test | State | Date Completed | Tickets | Notes |
IG-ST-1 New Site to GPO IG | Color(green,Pass)? | 2014-08-01 | ||
IG-ST-2 Loop topology | Color(green,Pass)? | 2014-08-01 | ||
IG-ST-3 Linear topology | Color(green,Pass)? | 2014-08-04 | ||
IG-ST-4 New Site to GPO EG | Color(green,Pass)? | 2014-08-04 | 100 Mbps link capacity (see Rspec) | |
IG-ST-5 Site Information | Color(#63B8FF,In Progress)? | Waiting for site nick-name | ||
IG-ST-6 OpenFlow topology | Color(green,Pass)? | 2014-08-05 | over ION |
Stanford University
Site Status:
Stitching Confirmation Tests Logs: here
Stitching Request RSpecs: here
Test | State | Date Completed | Tickets | Notes |
IG-ST-1 New Site to GPO IG | Color(green,Pass)? | 2014-02-06 | ||
IG-ST-2 Loop topology | Color(green,Pass)? | 2014-02-03 | ||
IG-ST-3 Linear topology | Color(green,Pass)? | 2014-02-03 | ||
IG-ST-4 New Site to GPO EG | Color(green,Pass)? | 2014-02-20 | ||
IG-ST-5 Site Information | Color(green,Pass)? | 2014-02-20 | ||
IG-ST-6 OpenFlow topology | Color(green,Pass)? | 2013-07-29 | over ION / AL2S being tested |
University of Chicago
Site Status: Pass
Stitching Confirmation Tests Logs: here
Stitching Request RSpecs: here
Test | State | Date Completed | Tickets | Notes |
IG-ST-1 New Site to GPO IG | ||||
IG-ST-2 Loop topology | ||||
IG-ST-3 Linear topology | ||||
IG-ST-4 New Site to GPO EG | ||||
IG-ST-5 Site Information | ||||
IG-ST-6 OpenFlow topology | AL2S-only |
University of Illinois
Site Status: Pass
Stitching Confirmation Tests Logs: here
Stitching Request RSpecs: here
Test | State | Date Completed | Tickets | Notes |
IG-ST-1 New Site to GPO IG | Color(green,Pass)? | 2013-12-11 | ||
IG-ST-2 Loop topology | Color(green,Pass)? | 2013-12-11 | ||
IG-ST-3 Linear topology | Color(green,Pass)? | 2013-12-11 | ||
IG-ST-4 New Site to GPO EG | Color(green,Pass)? | 2013-12-11 | ||
IG-ST-5 Site Information | Color(green,Pass)? | 2013-12-11 | ||
IG-ST-6 OpenFlow topology | Color(green,Pass)? | 2013-07-30 | over ION |
University of Kentucky PKS2
Site Status:
Stitching Confirmation Tests Logs: here
Stitching Request RSpecs: here
Test | State | Date Completed | Tickets | Notes |
IG-ST-1 New Site to GPO IG | Color(green,Pass)? | 2014-09-09 | ||
IG-ST-2 Loop topology | Color(green,Pass)? | 2014-09-09 | ||
IG-ST-3 Linear topology | Color(green,Pass)? | 2014-09-09 | ||
IG-ST-4 New Site to GPO EG | Color(green,Pass)? | 2014-09-09 | ||
IG-ST-5 Site Information | Color(#63B8FF,In Progress)? | Waiting for site nick-name | ||
IG-ST-6 OpenFlow topology | Color(orange,Blocked)? | No proxy on Flowvisor host for OF switch?? |
University of Missouri
Site Status: Pass
Stitching Confirmation Tests Logs: here
Stitching Request RSpecs: here
Test | State | Date Completed | Tickets | Notes |
IG-ST-1 New Site to GPO IG | Color(green,Pass)? | 2013-11-19 | ||
IG-ST-2 Loop topology | Color(green,Pass)? | 2013-11-19 | ||
IG-ST-3 Linear topology | Color(green,Pass)? | 2013-11-20 | ||
IG-ST-4 New Site to GPO EG | Color(green,Pass)? | 2013-11-20 | ||
IG-ST-5 Site Information | Color(green,Pass)? | 2013-11-20 | #1154 | over ION / AL2S being |
University of Wisconsin
Site Status:
Stitching Confirmation Tests Logs: here
Stitching Request RSpecs: here
Test | State | Date Completed | Tickets | Notes |
IG-ST-1 New Site to GPO IG | Color(green,Pass)? | 2013-11-21 | ||
IG-ST-2 Loop topology | Color(green,Pass)? | 2013-11-22 | ||
IG-ST-3 Linear topology | Color(green,Pass)? | 2013-11-22 | ||
IG-ST-4 New Site to GPO EG | Color(green,Pass)? | 2013-12-03 | ||
IG-ST-5 Site Information | Color(green,Pass)? | 2013-11-23 | #1154 | |
IG-ST-6 OpenFlow topology | Color(green,Pass)? | 2013-07-29 | over ION |