Changes between Version 13 and Version 14 of WIMXUCLA


Ignore:
Timestamp:
08/31/10 19:47:00 (14 years ago)
Author:
Giovanni Pau
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • WIMXUCLA

    v13 v14  
    4747
    4848|| Step || Description || Planned || Started || Completed || Comment ||
    49 ||   1  || Identify Outdoor Site on Campus || - || Completed  || -|| Identified 2 locations: 1 on the hill: Spraul Hall one of the student housing building; the second one on Boelter Hall CSD. Initial Setup on Boelter Hall for Testing purposes. The WiFi sites are 6 and they cover the whole campus; topology posted as picture below. ||
     49||   1  || Identify Outdoor Site on Campus || - || Completed  || -|| Identified 2 locations: 1 on the hill: Sproul Hall one of the student housing building; the second one on Boelter Hall CSD. Initial Setup on Boelter Hall for Testing purposes. The WiFi sites are 6 and they cover the whole campus; topology posted as picture below. ||
    5050|| 2 || Obtain FCC License || - || Completed || - || 2 Year License Granted, Additional years if needed will be requested. The license has 2 frequencies 2,575MHz an 2,590MHz. 2 Campus Locations are authorized to transmit.||
    51 || 3 || Identify Indoor Equipment Room on Campus || - || Completed || - ||2 Locations 1 in Boelter Hall and 1 in Spraul Hall.||
     51|| 3 || Identify Indoor Equipment Room on Campus || - || Completed || - ||2 Locations 1 in Boelter Hall and 1 in Sproul Hall.||
    5252|| 4 || Install Wiring at Outdoor Site and to Indoor Equipment Room || - || Started || - ||Indoor Completed. Outdoor completion expected on 9/20- pending Tower Arrival||
    5353|| 5 || Install Pole at Outdoor Site and Ground  || - || Started || - || Must is purchased, the 8' tall aluminum tower is ordered but not yet delivered.||