    4848|| Step || Description || Planned || Started || Completed || Comment ||
    49 ||   1  || Identify Outdoor Site on Campus || - || Started  || -|| Likely site is top of student housing building, on a hill.||
    50 || 2 || Obtain FCC License || - || Started || - ||  ||
    51 || 3 || Identify Indoor Equipment Room on Campus || - || - || - || ||
    52 || 4 || Install Wiring at Outdoor Site and to Indoor Equipment Room || - || - || - || ||
    53 || 5 || Install Pole at Outdoor Site and Ground  || - || - || - || ||
    54 || 6 || Install Antenna at Outdoor Site  || - || - || - || ||
    55 || 7 || Install Base Station Outdoor Unit  || - || - || - || ||
    56 || 8 || Complete Wiring at Outdoor Site and to Indoor Equipment Room  || - || - || - || ||
    57 || 9 || Install Indoor Equipment Racks and Ground  || - || - || - || ||
    58 || 10 || Install 120VAC and -48VDC Power Feeds and/or Supplies  || - || - || - || ||
     49||   1  || Identify Outdoor Site on Campus || - || Completed  || -|| Likely site is top of student housing building, on a hill.||
     50|| 2 || Obtain FCC License || - || Completed || - ||  ||
     51|| 3 || Identify Indoor Equipment Room on Campus || - || Completed || - || ||
     52|| 4 || Install Wiring at Outdoor Site and to Indoor Equipment Room || - || Completed || - || ||
     53|| 5 || Install Pole at Outdoor Site and Ground  || - || Started || - || ||
     54|| 6 || Install Antenna at Outdoor Site  || - || Started|| - || ||
     55|| 7 || Install Base Station Outdoor Unit  || - || Started || - || ||
     56|| 8 || Complete Wiring at Outdoor Site and to Indoor Equipment Room  || - || Started || - || ||
     57|| 9 || Install Indoor Equipment Racks and Ground  || - || Started || - || ||
     58|| 10 || Install 120VAC and -48VDC Power Feeds and/or Supplies  || - || Started || - || ||
    5959|| 11 || Install Base Station Indoor Unit  || - || - || - || ||
    6060|| 12 || Complete Wiring of Base Station Indoor Unit  || - || - || - || ||
    6161|| 13 || Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units  || - || - || - || ||
    6262|| 14 || Install Ethernet (VLAN) Switch, or Identify Existing Capacity  || - || - || - || ||
    63 || 15 || Install Linux Server(s) and Software || - || - || - || ||
     63|| 15 || Install Linux Server(s) and Software || - || Started-for WiFi || - || ||
    6464|| 16 || Connect Backbone Network  || - || - || - || ||
    6565|| 17 || Provide Reference Client Platform  || - || - || - || ||