wiki:GENIRacksHome/USIgniteInstageniRacks/ConfirmationTestStatus

Version 31 (modified by lnevers@bbn.com, 8 years ago) (diff)

--

US Ignite InstaGENI Confirmation Test Status

This page captures the status for new US Ignite InstaGENI sites that are validated by the GPO upon completion of the US Ignite GENI Rack Site Installation Checklist?. The GPO executes Administration, Experiment, Network VLAN Stitching and Monitoring tests to confirm the ability of a New Site to operate within the GENI environment. Tests are defined in the US Ignite Site Confirmation Tests page.

Site Status

Confirmation Tests In Progress:

University of Louisiana USIgnite at Lafayette,

Completed Confirmation Tests successfully:

Template Site GPO

Status Legend

Overall InstaGENI Site Status may be one of the following:

  • Pass - Site confirmation tests completed successfully and site is ready for Experimenters.
  • Pass: most criteria - Site partially confirmed with documented exceptions.
  • Blocked - Site confirmation tests blocked by tracked issue.
  • In Progress - Site confirmation tests in progress.

Individual Confirmation Test Status status may be one of the following:


US Ignite InstaGENI Sites Test Status

University of Louisiana US Ignite - Lafayette

Overall Site Status:_ In Progress
Confirmation Test Start Date: 2017-05-08
Confirmation Test Completion Date: <<insert_date_here>>

Test State CompletedTicketsNotes
IG-CT-1 VM Resources
IG-CT-2 Bare Metal and VM
IG-CT-3 Multi-site Tunnel
IG-CT-5 Monitoring
IG-CT-6 Administrative
IG-ST-1 New Site to GPO IG
IG-ST-2 Loop topology
IG-ST-3 Linear topology
IG-ST-4 New Site to GPO EG
IG-ST-5 Site Information
IG-ST-6 OpenFlow topology


Confirmation Tests Logs: University of Louisiana US Ignite - Lafayette

Request RSpecs: <<insert_link_to_repo_rspec1>>.


University of Vermont - Burlington

Overall Site Status:_ In Progress
Confirmation Test Start Date: 2017-05-08
Confirmation Test Completion Date: <<insert_date_here>>

Test State CompletedTicketsNotes
IG-CT-1 VM Resources
IG-CT-2 Bare Metal and VM
IG-CT-3 Multi-site Tunnel
IG-CT-5 Monitoring
IG-CT-6 Administrative
IG-ST-1 New Site to GPO IG
IG-ST-2 Loop topology
IG-ST-3 Linear topology
IG-ST-4 New Site to GPO EG
IG-ST-5 Site Information
IG-ST-6 OpenFlow topology


Confirmation Tests Logs: University of Vermont - Burlington

Request RSpecs: <<insert_link_to_repo_rspec1>>.


University of Texas - Dallas

Overall Site Status:_ <<insert_site_status>>
Confirmation Test Start Date: <<insert_date_here>>
Confirmation Test Completion Date: <<insert_date_here>>

Test State CompletedTicketsNotes
IG-CT-1 VM Resources
IG-CT-2 Bare Metal and VM
IG-CT-3 Multi-site Tunnel
IG-CT-4
IG-CT-5 Monitoring
IG-CT-6 Administrative
IG-ST-1 New Site to GPO IG
IG-ST-2 Loop topology
IG-ST-3 Linear topology
IG-ST-4 New Site to GPO EG
IG-ST-5 Site Information
IG-ST-6 OpenFlow topology


Confirmation Tests Logs: University of Texas - Dallas

Request RSpecs: <<insert_link_to_repo_rspec1>>.


Template Site GPO US Ignite - Cambridge

Overall Site Status:_ Pass: most criteria
Confirmation Test Start Date: 2017-02-22
Confirmation Test Completion Date: <<insert_date_here>>

Test State CompletedTicketsNotes
IG-CT-1 VM Resources Color(green,Pass)? 2017-02-24
IG-CT-2 Bare Metal and VMColor(green,Pass)? 2017-02-24
IG-CT-3 Multi-site Tunnel Color(green,Pass)? 2017-02-27 GRE IP table patching
IG-CT-5 Monitoring N/A Not configured for template rack
IG-CT-6 Administrative Color(green,Pass)?2017-02-28
IG-ST-1 New Site to GPO IG Color(green,Pass)?2017-02-27
IG-ST-2 Loop topology Color(red,Fail)? 2017-02-28 Multi-link problem specific to GPO rack, not reproducible at other sites.
IG-ST-3 Linear topology Color(red,Fail)? 2017-02-28 Multi-link problem specific to GPO rack, not reproducible at other sites.
IG-ST-4 New Site to GPO EGColor(green,Pass)? 2017-02-27
IG-ST-5 Site Information N/A Temporary site
IG-ST-6 OpenFlow topology Color(green,Pass)?2017-02-22


Confirmation Tests Logs: GPO US Ignite Template Site

Request RSpecs: <<insert_link_to_repo_rspec1>>.