Changes between Version 8 and Version 9 of 2012-09_UEN_GENI_Status_Report
- Timestamp:
- 09/22/12 20:01:24 (12 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
2012-09_UEN_GENI_Status_Report
v8 v9 3 3 == Period: Through 9/30/2012 == 4 4 5 I. Major accomplishments ¶ 6 A. Milestones achieved 5 == I. Major accomplishments ¶ == 6 === A. Milestones achieved === 7 7 || '''Milestone''' || '''Status''' || '''Begin Date''' || '''End Date''' || '''Notes''' || 8 8 || Acquire and test HP aggregate switch for ProtoGENI and first GENI rack || Complete || April 2012 || June 15, 2012 || First rack is Rob's InstaGENI rack || … … 13 13 14 14 15 B. Deliverables made 15 === B. Deliverables made === 16 16 * GEC 12: attended by Steve Corbato and Joe Breen with poster 17 17 * GEC 13: attended by Steve Corbato and Joe Breen … … 19 19 * FOAM and Flowvisor installation complete 20 20 21 II. Description of work performed during last quarter 21 == II. Description of work performed during last quarter == 22 22 A. Activities and findings 23 23