  • 2012-09_UEN_GENI_Status_Report

    v8 v9  
    33== Period: Through 9/30/2012 ==
    44
    5  I. Major accomplishments ¶
    6 A. Milestones achieved
     5== I. Major accomplishments ¶ ==
     6=== A. Milestones achieved ===
    77|| '''Milestone''' ||   '''Status''' ||         '''Begin Date''' ||     '''End Date''' ||       '''Notes''' ||
    88|| Acquire and test HP aggregate switch for ProtoGENI and first GENI rack ||    Complete ||     April 2012 ||   June 15, 2012 || First rack is Rob's InstaGENI rack ||
     
    1313
    1414
    15 B. Deliverables made
     15=== B. Deliverables made ===
    1616 * GEC 12: attended by Steve Corbato and Joe Breen with poster
    1717 * GEC 13: attended by Steve Corbato and Joe Breen
     
    1919 * FOAM and Flowvisor installation complete
    2020
    21 II. Description of work performed during last quarter
     21== II. Description of work performed during last quarter ==
    2222 A. Activities and findings
    2323