Milestone | Status | Begin Date | End Date | Notes
|
Acquire and test HP aggregate switch for ProtoGENI and first GENI rack | Complete | April 2012 | June 15, 2012 | First rack is Rob's InstaGENI rack
|
Deploy aggregate switch and bring new connections to Univ of Utah and UEN | Complete | June 15, 2012 | July 6, 2012 | Dependent on testing of InstaGENI rack because implementation involves interruption of current ProtoGENI infrastructure
|
Support multi-campus demo that includes new resources from this deployment and existing meso-scale resources. (GEC July, 2012) | Complete | July 1, 2012 | Aug 22, 2012 | Did not use UEN aggregate switch - Used only ProtoGENI direct connection into the GENI backbone. Could not interrupt the experiments for the data plane cutover
|
Integrate and test with other existing Internet2 and NLR OpenFlow meso-scale deployments and GENI racks. (Sept 30, 2012) | | 9/23/2012 | Sept 30, 2012 |
|
Make Switch resources available to NSF experimenters | | Sept 23, 2012 | Sept 23, 2012 |
|