Changes between Version 5 and Version 6 of 2012-09_UEN_GENI_Status_Report


Ignore:
Timestamp:
09/22/12 19:50:08 (12 years ago)
Author:
joe.breen@utah.edu
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • 2012-09_UEN_GENI_Status_Report

    v5 v6  
    77|| '''Milestone''' ||   '''Status''' ||         '''Begin Date''' ||     '''End Date''' ||       '''Notes''' ||
    88|| Acquire and test HP aggregate switch for ProtoGENI and first GENI rack ||    Complete ||     April 2012 ||   June 15, 2012 || First rack is Rob's InstaGENI rack
    9 || Deploy aggregate switch and bring new connections to Univ of Utah and UEN ||         June 15, 2012 ||        July 6, 2012 || Dependent on testing of InstaGENI rack because implementation involves interruption of current ProtoGENI infrastructure ||
    10 || Support multi-campus demo that includes new resources from this deployment and existing meso-scale resources. (GEC July, 2012) ||            July 8, 2012    ||
    11 || Integrate and test with other existing Internet2 and NLR OpenFlow meso-scale deployments and GENI racks. (Sept 30, 2012) ||                  Aug 30, 2012    
     9|| Deploy aggregate switch and bring new connections to Univ of Utah and UEN || Complete ||     June 15, 2012 ||        July 6, 2012 || Dependent on testing of InstaGENI rack because implementation involves interruption of current ProtoGENI infrastructure || ||
     10|| Support multi-campus demo that includes new resources from this deployment and existing meso-scale resources. (GEC July, 2012) || Complete || July 8, 2012 || ||
     11|| Integrate and test with other existing Internet2 and NLR OpenFlow meso-scale deployments and GENI racks. (Sept 30, 2012) ||  || Aug 30, 2012 || ||   
    1212|| Make Switch resources available to NSF experimenters ||                      Sept 30, 2012 ||
    1313