Milestone | Status | Begin Date | End Date | Notes
|
Acquire and test HP aggregate switch for ProtoGENI and first GENI rack | Complete | April 2012 | June 15, 2012 | First rack is Rob's InstaGENI rack
|
Deploy aggregate switch and bring new connections to Univ of Utah and UEN | June 15, 2012 | July 6, 2012 | Dependent on testing of InstaGENI rack because implementation involves interruption of current ProtoGENI infrastructure
|
Support multi-campus demo that includes new resources from this deployment and existing meso-scale resources. (GEC July, 2012) | July 8, 2012
|
Integrate and test with other existing Internet2 and NLR OpenFlow meso-scale deployments and GENI racks. (Sept 30, 2012) | Aug 30, 2012
|
Make Switch resources available to NSF experimenters | Sept 30, 2012
|