7 | | Milestone Status Begin Date End Date Notes |
8 | | Acquire and test HP aggregate switch for ProtoGENI and first GENI rack Complete April 2012 June 15, 2012 First rack is Rob's InstaGENI rack |
9 | | Deploy aggregate switch and bring new connections to Univ of Utah and UEN June 15, 2012 July 6, 2012 Dependent on testing of InstaGENI rack because implementation involves interruption of current ProtoGENI infrastructure |
10 | | Support multi-campus demo that includes new resources from this deployment and existing meso-scale resources. (GEC July, 2012) July 8, 2012 |
11 | | Integrate and test with other existing Internet2 and NLR OpenFlow meso-scale deployments and GENI racks. (August 30, 2012) Aug 30, 2012 |
12 | | Make Switch resources available to NSF experimenters Sept 30, 2012 |
| 7 | || '''Milestone''' || '''Status''' || '''Begin Date''' || '''End Date''' || '''Notes''' || |
| 8 | || Acquire and test HP aggregate switch for ProtoGENI and first GENI rack || Complete || April 2012 || June 15, 2012 || First rack is Rob's InstaGENI rack |
| 9 | || Deploy aggregate switch and bring new connections to Univ of Utah and UEN || June 15, 2012 || July 6, 2012 || Dependent on testing of InstaGENI rack because implementation involves interruption of current ProtoGENI infrastructure || |
| 10 | || Support multi-campus demo that includes new resources from this deployment and existing meso-scale resources. (GEC July, 2012) || July 8, 2012 || |
| 11 | || Integrate and test with other existing Internet2 and NLR OpenFlow meso-scale deployments and GENI racks. (Sept 30, 2012) || Aug 30, 2012 |
| 12 | || Make Switch resources available to NSF experimenters || Sept 30, 2012 || |