    3636[[MilestoneDate(WIMXCOLUM: S2.b Install the WiMax base station kit and antennas)]][[BR]]
    3737
     38=== Campus Installation Checklist ===
     39
     40University of Colorado at Boulder [[BR]]
     41
     42Contact(s):  [[BR]]
     43PI: Dirk Grunwald  Dirk.Grunwald@Colorado.edu [[BR]]
     44
     45Step 1)  Identify Outdoor Site on Campus:    planned/started/completed x/x/10 [[BR]]
     46
     47Step 2)  Obtain FCC License:  planned/started/completed x/x/10 [[BR]]
     48
     49Step 3)  Identify Indoor Equipment Room on Campus:  planned/started/completed x/x/10 [[BR]]
     50
     51Step 4)  Install Wiring at Outdoor Site and to Indoor Equipment Room:  planned/started/completed x/x/10 [[BR]]
     52
     53Step 5)  Install Pole at Outdoor Site and Ground:  planned/started/completed x/x/10 [[BR]]
     54
     55Step 6)  Install Antenna at Outdoor Site:  planned/started/completed x/x/10 [[BR]]
     56
     57Step 7)  Install Base Station Outdoor Unit:  planned/started/completed x/x/10 [[BR]]
     58
     59Step 8)  Complete Wiring at Outdoor Site and to Indoor Equipment Room:  planned/started/completed x/x/10 [[BR]]
     60
     61Step 9)  Install Indoor Equipment Racks and Ground:  planned/started/completed x/x/10 [[BR]]
     62
     63Step 10)  Install 120VAC and -48VDC Power Feeds and/or Supplies:  planned/started/completed x/x/10 [[BR]]
     64
     65Step 11)  Install Base Station Indoor Unit:  planned/started/completed x/x/10 [[BR]]
     66
     67Step 12)  Complete Wiring of Base Station Indoor Unit:  planned/started/completed x/x/10 [[BR]]
     68
     69Step 13)  Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units:  planned/started/completed x/x/10 [[BR]]
     70
     71Step 14)  Install Ethernet (VLAN) Switch, or Identify Existing Capacity:  planned/started/completed x/x/10 [[BR]]
     72
     73Step 15)  Install Linux Server(s) and Software:  planned/started/completed x/x/10 [[BR]]
     74
     75Step 16)  Connect Backbone Network:  planned/started/completed x/x/10 [[BR]]
     76
     77Step 17)  Provide Reference Client Platform:  planned/started/completed x/x/10 [[BR]]
     78
     79Step 18)  Inital Check-Out of Campus WiMAX Testbed:  planned/started/completed x/x/10 [[BR]]