Possible change to milestone date.
Reported by: | Vic Thomas | Owned by: | Vic Thomas |
---|---|---|---|
Priority: | major | Milestone: | MeasurementSys: S1.a System interface design specification - |
Component: | GPO | Version: | SPIRAL1 |
Keywords: | Cc: | ||
Dependencies: |
Description (last modified by )
PI indicated that he might need to adjust delivery date for this milestone because he started the project at less than full staffing (on risk funding). Vic Thomas has requested updated date from Paul Barford.
- Emailed Barford on 15 Jan 2009 asking about milestone delivery. He responded they'd be completed "next week".
- Emailed Barford on 30 jan 2009 asking about milestone delivery. He responded they'd be completed "next week". Set milestone due date to 30 Jan based on comment by Barford that delivery dates may be delayed given they got under contract on Oct. 27 and not Oct. 1.
- Emailed Barford on 17 Feb 2009 asking about milestone delivery.
Change History (3)
comment:1 Changed 15 years ago by
Owner: | changed from somebody to Vic Thomas |
---|---|
Status: | new → assigned |
comment:2 Changed 15 years ago by
Description: | modified (diff) |
---|
comment:3 Changed 15 years ago by
Resolution: | → fixed |
---|---|
Status: | assigned → closed |
Note: See
TracTickets for help on using
tickets.
4/14/09: Changed milestone due date to 4/27. Paul Barford will post updated measurement system design document by then. Created TIcket #79 and assigned to PB. Change approved by Henry on 3/31.