28 | | • S6.a Complete and review design for layer 2 SDN/OpenFlow research exchange with GENI community (March 31, 2014) |
29 | | • S6.b Develop prototype implementation and operations tools with working interfaces to GENI rack resources and APIs. (March 31, 2014) |
30 | | • S6.c Add experimenter tools (including controller) to prototype implementation (June 30, 2014] |
31 | | • S6.d Test services, software and hardware implementations with other GENI AMs, GENI stitching and one prototype exchange research network (not a GENI network) (June 30, 2014) |
32 | | • S6.e Dry run GEC21 demonstration of the integrated exchange (September 30, 2014) (GEC21 is planned for Oct 21-23) |
33 | | • S6.f Begin operating exchange with selected early integration partners (September 30, 2014) |
| 28 | * S6.a Complete and review design for layer 2 SDN/OpenFlow research exchange with GENI community (March 31, 2014) |
| 29 | * S6.b Develop prototype implementation and operations tools with working interfaces to GENI rack resources and APIs. (March 31, 2014) |
| 30 | * S6.c Add experimenter tools (including controller) to prototype implementation (June 30, 2014] |
| 31 | * S6.d Test services, software and hardware implementations with other GENI AMs, GENI stitching and one prototype exchange research network (not a GENI network) (June 30, 2014) |
| 32 | * S6.e Dry run GEC21 demonstration of the integrated exchange (September 30, 2014) (GEC21 is planned for Oct 21-23) |
| 33 | * S6.f Begin operating exchange with selected early integration partners (September 30, 2014) |