155 | | || 1 || Identify Outdoor Site on Campus || - || - || - || - || - || - || - || || |
156 | | || 2 || Obtain FCC License || - || - || - || - || - || - || - || || |
157 | | || 3 || Identify Indoor Equipment Room on Campus || - || - || - || - || - || - || - || || |
158 | | || 4 || Install Wiring at Outdoor Site and to Indoor Equipment Room || - || - || - || - || - || - || - || || |
159 | | || 5 || Install Pole at Outdoor Site and Ground || - || - || - || - || - || - || - || || |
160 | | || 6 || Install Antenna at Outdoor Site || - || - || - || - || - || - || - || || |
161 | | || 7 || Install Base Station Outdoor Unit || - || - || - || - || - || - || - || || |
162 | | || 8 || Complete Wiring at Outdoor Site and to Indoor Equipment Room || - || - || - || - || - || - || - || || |
163 | | || 9 || Install Indoor Equipment Racks and Ground || - || - || - || - || - || - || - || || |
164 | | || 10 || Install 120VAC and -48VDC Power Feeds and/or Supplies || - || - || - || - || - || - || - || || |
165 | | || 11 || Install Base Station Indoor Unit || - || - || - || - || - || - || - || || |
166 | | || 12 || Complete Wiring of Base Station Indoor Unit || - || - || - || - || - || - || - || || |
167 | | || 13 || Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units || - || - || - || - || - || - || - || || |
168 | | || 14 || Install Ethernet (VLAN) Switch, or Identify Existing Capacity || - || - || - || - || - || - || - || || |
169 | | || 15 || Install Linux Server(s) and Software || - || - || - || - || - || - || - || || |
170 | | || 16 || Connect Backbone Network || - || - || - || - || - || - || - || || |
171 | | || 17 || Provide Reference Client Platform || - || - || - || - || - || - || - || || |
172 | | || 18 || Initial Check-Out of Campus WiMAX Testbed || - || - || - || - || - || - || - || || |
| 155 | || 1 || Identify Outdoor Site on Campus || - || - || - || - || - || - || - || |
| 156 | || 2 || Obtain FCC License || - || - || - || - || - || - || - || |
| 157 | || 3 || Identify Indoor Equipment Room on Campus || - || - || - || - || - || - || - || |
| 158 | || 4 || Install Wiring at Outdoor Site and to Indoor Equipment Room || - || - || - || - || - || - || - || |
| 159 | || 5 || Install Pole at Outdoor Site and Ground || - || - || - || - || - || - || - || |
| 160 | || 6 || Install Antenna at Outdoor Site || - || - || - || - || - || - || - || |
| 161 | || 7 || Install Base Station Outdoor Unit || - || - || - || - || - || - || - || |
| 162 | || 8 || Complete Wiring at Outdoor Site and to Indoor Equipment Room || - || - || - || - || - || - || - || |
| 163 | || 9 || Install Indoor Equipment Racks and Ground || - || - || - || - || - || - || - || |
| 164 | || 10 || Install 120VAC and -48VDC Power Feeds and/or Supplies || - || - || - || - || - || - || - || |
| 165 | || 11 || Install Base Station Indoor Unit || - || - || - || - || - || - || - || |
| 166 | || 12 || Complete Wiring of Base Station Indoor Unit || - || - || - || - || - || - || - || |
| 167 | || 13 || Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units || - || - || - || - || - || - || - || |
| 168 | || 14 || Install Ethernet (VLAN) Switch, or Identify Existing Capacity || - || - || - || - || - || - || - || |
| 169 | || 15 || Install Linux Server(s) and Software || - || - || - || - || - || - || - || |
| 170 | || 16 || Connect Backbone Network || - || - || - || - || - || - || - || |
| 171 | || 17 || Provide Reference Client Platform || - || - || - || - || - || - || - || |
| 172 | || 18 || Initial Check-Out of Campus WiMAX Testbed || - || - || - || - || - || - || - || |