    140140==  8.  Campus Installation Checklist ==
    141141
    142 Campus installation checklist, for each site:[[BR]]
    143  
    144 Step 1)  Identify Outdoor Site on Campus:    planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    145 
    146 Step 2)  Obtain FCC License:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    147 
    148 Step 3)  Identify Indoor Equipment Room on Campus:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    149 
    150 Step 4)  Install Wiring at Outdoor Site and to Indoor Equipment Room:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    151 
    152 Step 5)  Install Pole at Outdoor Site and Ground:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    153 
    154 Step 6)  Install Antenna at Outdoor Site:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    155 
    156 Step 7)  Install Base Station Outdoor Unit:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    157 
    158 Step 8)  Complete Wiring at Outdoor Site and to Indoor Equipment Room:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    159 
    160 Step 9)  Install Indoor Equipment Racks and Ground:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    161 
    162 Step 10)  Install 120VAC and -48VDC Power Feeds and/or Supplies:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    163 
    164 Step 11)  Install Base Station Indoor Unit:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    165 
    166 Step 12)  Complete Wiring of Base Station Indoor Unit:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    167 
    168 Step 13)  Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    169 
    170 Step 14)  Install Ethernet (VLAN) Switch, or Identify Existing Capacity:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    171 
    172 Step 15)  Install Linux Server(s) and Software:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    173 
    174 Step 16)  Connect Backbone Network:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    175 
    176 Step 17)  Provide Reference Client Platform:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
    177 
    178 Step 18)  Inital Check-Out of Campus WiMAX Testbed:  planned x/x/10;  started y/y/10;  completed z/z/10[[BR]]
     142Campus Installation Checklist, for each site [[BR]]
     143
     144Contact(s):    [[BR]]
     145
     146
     147Step 1)  Identify Outdoor Site on Campus:    planned/started/completed x/x/10 [[BR]]
     148
     149Step 2)  Obtain FCC License:  planned/started/completed x/x/10 [[BR]]
     150
     151Step 3)  Identify Indoor Equipment Room on Campus:  planned/started/completed x/x/10 [[BR]]
     152
     153Step 4)  Install Wiring at Outdoor Site and to Indoor Equipment Room:  planned/started/completed x/x/10 [[BR]]
     154
     155Step 5)  Install Pole at Outdoor Site and Ground:  planned/started/completed x/x/10 [[BR]]
     156
     157Step 6)  Install Antenna at Outdoor Site:  planned/started/completed x/x/10 [[BR]]
     158
     159Step 7)  Install Base Station Outdoor Unit:  planned/started/completed x/x/10 [[BR]]
     160
     161Step 8)  Complete Wiring at Outdoor Site and to Indoor Equipment Room:  planned/started/completed x/x/10 [[BR]]
     162
     163Step 9)  Install Indoor Equipment Racks and Ground:  planned/started/completed x/x/10 [[BR]]
     164
     165Step 10)  Install 120VAC and -48VDC Power Feeds and/or Supplies:  planned/started/completed x/x/10 [[BR]]
     166
     167Step 11)  Install Base Station Indoor Unit:  planned/started/completed x/x/10 [[BR]]
     168
     169Step 12)  Complete Wiring of Base Station Indoor Unit:  planned/started/completed x/x/10 [[BR]]
     170
     171Step 13)  Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units:  planned/started/completed x/x/10 [[BR]]
     172
     173Step 14)  Install Ethernet (VLAN) Switch, or Identify Existing Capacity:  planned/started/completed x/x/10 [[BR]]
     174
     175Step 15)  Install Linux Server(s) and Software:  planned/started/completed x/x/10 [[BR]]
     176
     177Step 16)  Connect Backbone Network:  planned/started/completed x/x/10 [[BR]]
     178
     179Step 17)  Provide Reference Client Platform:  planned/started/completed x/x/10 [[BR]]
     180
     181Step 18)  Inital Check-Out of Campus WiMAX Testbed:  planned/started/completed x/x/10 [[BR]]