| 140 | Campus installation steps and status, for each site: |
| 141 | |
| 142 | Step 1) Identify Outdoor Site on Campus: Planned Started Completed when [[BR]] |
| 143 | Step 2) 2 Obtain FCC License: Planned Started Completed when [[BR]] |
| 144 | Step 3) 3 Identify Indoor Equipment Room on Campus: Planned Started Completed when [[BR]] |
| 145 | Step 4) 4 Install Wiring at Outdoor Site and to Indoor Equipment Room: Planned Started Completed when [[BR]] |
| 146 | Step 5) 5 Install Pole at Outdoor Site and Ground: Planned Started Completed when [[BR]] |
| 147 | Step 6) 6 Install Antenna at Outdoor Site: Planned Started Completed when [[BR]] |
| 148 | Step 7) 7 Install Base Station Outdoor Unit: Planned Started Completed when [[BR]] |
| 149 | Step 8) 8 Complete Wiring at Outdoor Site and to Indoor Equipment Room: Planned Started Completed when [[BR]] |
| 150 | Step 9) 9 Install Indoor Equipment Racks and Ground: Planned Started Completed when [[BR]] |
| 151 | Step 10) 10 Install 120VAC and -48VDC Power Feeds and/or Supplies: Planned Started Completed when [[BR]] |
| 152 | Step 11) 11 Install Base Station Indoor Unit: Planned Started Completed when [[BR]] |
| 153 | Step 12) 12 Complete Wiring of Base Station Indoor Unit: Planned Started Completed when [[BR]] |
| 154 | Step 13) 13 Initial Check-Out of Antenna and Base Station Outdoor and Indoor … : Planned Started Completed when [[BR]] |
| 155 | Step 14) 14 Install Ethernet (VLAN) Switch, or Identify Existing Capacity: Planned Started Completed when [[BR]] |
| 156 | Step 15) 15 Install Linux Server(s) and Software: Planned Started Completed when [[BR]] |
| 157 | Step 16) 16 Connect Backbone Network: Planned Started Completed when [[BR]] |
| 158 | Step 17) 17 Provide Reference Client Platform: Planned Started Completed when [[BR]] |
| 159 | Step 18) 18 Inital Check-Out of Campus WiMAX Testbed: Planned Started Completed when [[BR]] |
| 160 | |
| 161 | |