Changes between Version 36 and Version 37 of WiMAXInteg/CampusInstallation


Ignore:
Timestamp:
02/08/10 09:45:03 (14 years ago)
Author:
hmussman@bbn.com
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • WiMAXInteg/CampusInstallation

    v36 v37  
    1414 * Base Staion Indoor Unit, equipped equipped for 1-Sector Configuration, with one Network Interface (NW INTFC) card and one Channel Card (CHC).  Technical specification in Sec 2.6 of the [attachment:BS_INSTALLATION.pdf NEC Installation Manual for Base Station (IMN:BS)]
    1515
    16 
    17  * Linux Server, including the ASN-GW and ORBIT Mangement Framework software.
    18 
    19 
    20 ISSUE:  Need complete, detailed list.
     16 * One Linux Server, including the ASN-GW and ORBIT Mangement Framework software, sufficient for checkout and initial deployment;  may be sufficient for final depoyment configuration.
     17
     18
     19See ?? for complete, detailed list.
    2120
    2221
     
    2928 * Wiring between sites, preferably in conduit.
    3029
     30 * Zero to three Linux Servers, to accomodate desired final deployment configuration of the ASN-GW and ORBIT Mangement Framework software.
     31 
    3132 * Ethernet switch for multiple VLANs.
    3233
    33  * -48VDC power feed, or rectifier, for Base Staion Outdoor and Indoor Units.
     34 * -48VDC power supplies for Base Staion Outdoor and Indoor Units.
    3435
    3536 * 110VAC feed for Linux Servers, -48VDC rectifies (optional) and Ethernet Switch (optional).  Referably,should be provided by a UPS that bridges at least short power gaps.
    3637
    3738
    38 ISSUE:  Need complete list.
     39See Section 7.20 for complete, detailed list.
     40 
    3941
    4042Once the WiMAX base station kit has been installed on the campus, and is operational, the GPO can arrange the transfer of ownership from the NSF to the university.
     
    288290
    289291=== 7.18 Inital Check-Out of Campus WiMAX Testbed ===
     292
     293===  7.19  Campus Installation Checklist ===
     294
     295Campus Installation Checklist, for each site [[BR]]
     296
     297Contact(s):    [[BR]]
     298
     299
     300|| Step || Description || Planned || Started || Completed || Comment ||
     301||   1  || Identify Outdoor Site on Campus || - || - || - || ||
     302|| 2 || Obtain FCC License || - || - || - || ||
     303|| 3 || Identify Indoor Equipment Room on Campus || - || - || - || ||
     304|| 4 || Install Wiring at Outdoor Site and to Indoor Equipment Room || - || - || - || ||
     305|| 5 || Install Pole at Outdoor Site and Ground  || - || - || - || ||
     306|| 6 || Install Antenna at Outdoor Site  || - || - || - || ||
     307|| 7 || Install Base Station Outdoor Unit  || - || - || - || ||
     308|| 8 || Complete Wiring at Outdoor Site and to Indoor Equipment Room  || - || - || - || ||
     309|| 9 || Install Indoor Equipment Racks and Ground  || - || - || - || ||
     310|| 10 || Install 120VAC and -48VDC Power Feeds and/or Supplies  || - || - || - || ||
     311|| 11 || Install Base Station Indoor Unit  || - || - || - || ||
     312|| 12 || Complete Wiring of Base Station Indoor Unit  || - || - || - || ||
     313|| 13 || Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units  || - || - || - || ||
     314|| 14 || Install Ethernet (VLAN) Switch, or Identify Existing Capacity  || - || - || - || ||
     315|| 15 || Install Linux Server(s) and Software || - || - || - || ||
     316|| 16 || Connect Backbone Network  || - || - || - || ||
     317|| 17 || Provide Reference Client Platform  || - || - || - || ||
     318|| 18 || Initial Check-Out of Campus WiMAX Testbed  || - || - || - || ||
     319
     320
     321===  7.20  Campus Bill of Materials ===
     322
     323
     324===  7.21  Campus Installation and Deployment Plan Summary ===