Project Number
1724
Project Title
A Programmable Facility for Experimentation with Wireless Heterogeneity and Wide-area Mobility
a.k.a WIMXUWI
Technical Contacts
PI: Suman Banerjee suman@cs.wisc.edu
Participating Organizations
Wisconsin Wireless and NetworkinG Systems (WiNGS) laboratory
GPO Liaison System Engineer
Harry Mussman hmussman@geni.net
Scope
This project will integrate the currently operational, heterogeneous WiNGS-outdoor testbed spanning 60 square miles in and around Madison, WI, called MadBed, into GENI, and provide systematic low-level access to PHY/MAC features using the ORBIT Management Framework (OMF). It will add a “GENI WiMax Base Station Kit”, provided by an associated proposal, to the testbed to complement an existing Cisco/Navini WiMax base station. It will add a mobility services engine to the testbed, and enhance the user nodes, to allow the testbed to support a wide range of wireless experiments. It will provide a unique trial mechanism for opt-in users in the broader Madison area.
Current Capabilities
Milestones
Campus Installation Checklist
University of Wisconsin
Contact(s):
PI: Suman Banerjee suman@cs.wisc.edu
Step 1) Identify Outdoor Site on Campus: planned/started/completed x/x/10
Step 2) Obtain FCC License: planned/started/completed x/x/10
Step 3) Identify Indoor Equipment Room on Campus: planned/started/completed x/x/10
Step 4) Install Wiring at Outdoor Site and to Indoor Equipment Room: planned/started/completed x/x/10
Step 5) Install Pole at Outdoor Site and Ground: planned/started/completed x/x/10
Step 6) Install Antenna at Outdoor Site: planned/started/completed x/x/10
Step 7) Install Base Station Outdoor Unit: planned/started/completed x/x/10
Step 8) Complete Wiring at Outdoor Site and to Indoor Equipment Room: planned/started/completed x/x/10
Step 9) Install Indoor Equipment Racks and Ground: planned/started/completed x/x/10
Step 10) Install 120VAC and -48VDC Power Feeds and/or Supplies: planned/started/completed x/x/10
Step 11) Install Base Station Indoor Unit: planned/started/completed x/x/10
Step 12) Complete Wiring of Base Station Indoor Unit: planned/started/completed x/x/10
Step 13) Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units: planned/started/completed x/x/10
Step 14) Install Ethernet (VLAN) Switch, or Identify Existing Capacity: planned/started/completed x/x/10
Step 15) Install Linux Server(s) and Software: planned/started/completed x/x/10
Step 16) Connect Backbone Network: planned/started/completed x/x/10
Step 17) Provide Reference Client Platform: planned/started/completed x/x/10
Step 18) Inital Check-Out of Campus WiMAX Testbed: planned/started/completed x/x/10
Project Technical Documents
Quarterly Status Reports
Spiral 2 Connectivity
Related Projects
Attachments (4)
- 9-1-2010--UW-Madison-WIMXUWI.pptx (412.0 KB) - added by 14 years ago.
- wisc wimax GEC_10_Demo_Poster.pdf (1.2 MB) - added by 13 years ago.
-
Cisco_WiMAX_1.jpg (171.1 KB) - added by 12 years ago.
RSSI Data - Cisco - Route 80
-
NEC_WiMAX_1.jpg (971.5 KB) - added by 12 years ago.
NEC - RSSI - Route 80