Project Number
1724
Project Title
A Programmable Facility for Experimentation with Wireless Heterogeneity and Wide-area Mobility
a.k.a WIMXUWI
Technical Contacts
PI: Suman Banerjee suman@cs.wisc.edu
co-PI: Sateesh Addepalli sateeshk@cisco.com
Participating Organizations
Wisconsin Wireless and NetworkinG Systems (WiNGS) laboratory
Cisco Systems
GPO Liaison System Engineer
Harry Mussman hmussman@geni.net
Scope
This project will integrate the currently operational, heterogeneous WiNGS-outdoor testbed spanning 60 square miles in and around Madison, WI, called MadBed, into GENI, and provide systematic low-level access to PHY/MAC features using the ORBIT Management Framework (OMF). It will add a “GENI WiMax Base Station Kit”, provided by an associated proposal, to the testbed to complement an existing Cisco/Navini WiMax base station. It will add a mobility services engine to the testbed, and enhance the user nodes, to allow the testbed to support a wide range of wireless experiments. It will provide a unique trial mechanism for opt-in users in the broader Madison area.
Current Capabilities
Visit http://cs.wisc.edu/wings/projects/geni/ for more information
Milestones
MilestoneDate(WIMXUWI: S3.a Demonstration at GEC9 and Experimenter Outreach)?
MilestoneDate(WIMXUWI: S3.b Documentation and Code Release)?
MilestoneDate(WIMXUWI: S3.c Demonstration at GEC10 and Experimenter Outreach)?
MilestoneDate(WIMXUWI: S3.d Documentation and Code Release)?
MilestoneDate(WIMXUWI: S3.e Demonstration at GEC11 and Experimenter Outreach)?
MilestoneDate(WIMXUWI: S3.f Documentation and code release)?
Campus Installation Checklist
University of Wisconsin
Contact(s):
PI: Suman Banerjee suman@cs.wisc.edu
Step | Description | Planned | Started | Completed | Comment |
1 | Identify Outdoor Site on Campus | - | - | Completed | Have three good sites: one for Cisco, one for this kit, and would like to get a 2nd kit for third site. |
2 | Obtain FCC License | - | - | Completed | Have license owned by Educational Communications Board, using it with Cisco base station. Obtained second license for 2 NEC base stations |
3 | Identify Indoor Equipment Room on Campus | - | - | Completed | |
4 | Install Wiring at Outdoor Site and to Indoor Equipment Room | For NEC Units: Planned | - | For Cisco Unit: Completed | |
5 | Install Pole at Outdoor Site and Ground | For NEC Units: Planned | - | For Cisco Unit: Completed | |
6 | Install Antenna at Outdoor Site | For NEC Units: Planned | - | For Cisco Unit: Completed | |
7 | Install Base Station Outdoor Unit | For NEC Units: Planned | - | For Cisco Unit: Completed | |
8 | Complete Wiring at Outdoor Site and to Indoor Equipment Room | For NEC Units: Planned | - | For Cisco Unit: Completed | |
9 | Install Indoor Equipment Racks and Ground | For NEC Units: Planned | - | For Cisco Unit: Completed | |
10 | Install 120VAC and -48VDC Power Feeds and/or Supplies | For NEC Units: Planned | - | For Cisco Unit: Completed | |
11 | Install Base Station Indoor Unit | For NEC Units: Planned | - | For Cisco Unit: Completed | |
12 | Complete Wiring of Base Station Indoor Unit | For NEC Units: Planned | - | For Cisco Unit: Completed | |
13 | Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units | - | - | - | |
14 | Install Ethernet (VLAN) Switch, or Identify Existing Capacity | - | - | - | |
15 | Install Linux Server(s) and Software | - | - | - | |
16 | Connect Backbone Network | - | - | - | |
17 | Provide Reference Client Platform | - | - | - | |
18 | Initial Check-Out of Campus WiMAX Testbed | - | - | - |
Project Technical Documents
Quarterly Status Reports
Spiral 2 Review
2011 Q1 Status Report
Spiral 2 Connectivity
Related Projects
Attachments (4)
- 9-1-2010--UW-Madison-WIMXUWI.pptx (412.0 KB) - added by 14 years ago.
- wisc wimax GEC_10_Demo_Poster.pdf (1.2 MB) - added by 14 years ago.
-
Cisco_WiMAX_1.jpg (171.1 KB) - added by 13 years ago.
RSSI Data - Cisco - Route 80
-
NEC_WiMAX_1.jpg (971.5 KB) - added by 13 years ago.
NEC - RSSI - Route 80