Project Number
1768
Project Title
Deploying GENI WiMax in Colorado
a.k.a WIMXUCO
Technical Contacts
PI: Dirk Grunwald Dirk.Grunwald@Colorado.edu
Participating Organizations
University of Colorado at Boulder CS Dept.
GPO Liaison System Engineer
Harry Mussman hmussman@geni.net
Scope
This proposal will install and maintain a programmable WiMax base station at one of the existing University of Colorado Wide-Area Radio Testbed (WART) wireless network sites. It will use a “GENI WiMax Base Station Kit” provided by Rutgers.
Current Capabilities
Milestones
MilestoneDate(WIMXCOLUM: S2.a Redesign remote management/power system)?
MilestoneDate(WIMXCOLUM: S2.b Install the WiMax base station kit and antennas)?
Campus Installation Checklist
University of Colorado at Boulder
Contact(s):
PI: Dirk Grunwald Dirk.Grunwald@Colorado.edu
Step 1) Identify Outdoor Site on Campus: planned/started/completed x/x/10
Step 2) Obtain FCC License: planned/started/completed x/x/10
Step 3) Identify Indoor Equipment Room on Campus: planned/started/completed x/x/10
Step 4) Install Wiring at Outdoor Site and to Indoor Equipment Room: planned/started/completed x/x/10
Step 5) Install Pole at Outdoor Site and Ground: planned/started/completed x/x/10
Step 6) Install Antenna at Outdoor Site: planned/started/completed x/x/10
Step 7) Install Base Station Outdoor Unit: planned/started/completed x/x/10
Step 8) Complete Wiring at Outdoor Site and to Indoor Equipment Room: planned/started/completed x/x/10
Step 9) Install Indoor Equipment Racks and Ground: planned/started/completed x/x/10
Step 10) Install 120VAC and -48VDC Power Feeds and/or Supplies: planned/started/completed x/x/10
Step 11) Install Base Station Indoor Unit: planned/started/completed x/x/10
Step 12) Complete Wiring of Base Station Indoor Unit: planned/started/completed x/x/10
Step 13) Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units: planned/started/completed x/x/10
Step 14) Install Ethernet (VLAN) Switch, or Identify Existing Capacity: planned/started/completed x/x/10
Step 15) Install Linux Server(s) and Software: planned/started/completed x/x/10
Step 16) Connect Backbone Network: planned/started/completed x/x/10
Step 17) Provide Reference Client Platform: planned/started/completed x/x/10
Step 18) Inital Check-Out of Campus WiMAX Testbed: planned/started/completed x/x/10
Project Technical Documents
Quarterly Status Reports
Spiral 2 Connectivity
Related Projects
Attachments (1)
-
Spiral 2 Project Review template 9Jul10.pptx.pdf (854.3 KB) - added by 14 years ago.
Description of first year report (with antenna locations etc)
Download all attachments as: .zip