  • WIMXUCLA

    v4 v5  
    1313
    1414PI: Mario Gerla  gerla@cs.ucla.edu [[BR]]
     15Giovanni Pau [[BR]]
    1516
     17 
    1618=== Participating Organizations ===
    1719
     
    3537[[MilestoneDate(WIMXUCLA: S2.a Begin deployment of dual-mode vehicular nodes (WiFi and WiMax))]][[BR]]
    3638
     39=== Campus Installation Checklist ===
     40
     41UCLA [[BR]]
     42
     43Contact(s):  [[BR]]
     44
     45PI: Mario Gerla  gerla@cs.ucla.edu [[BR]]
     46
     47
     48Step 1)  Identify Outdoor Site on Campus:    planned/started/completed x/x/10 [[BR]]
     49
     50Step 2)  Obtain FCC License:  planned/started/completed x/x/10 [[BR]]
     51
     52Step 3)  Identify Indoor Equipment Room on Campus:  planned/started/completed x/x/10 [[BR]]
     53
     54Step 4)  Install Wiring at Outdoor Site and to Indoor Equipment Room:  planned/started/completed x/x/10 [[BR]]
     55
     56Step 5)  Install Pole at Outdoor Site and Ground:  planned/started/completed x/x/10 [[BR]]
     57
     58Step 6)  Install Antenna at Outdoor Site:  planned/started/completed x/x/10 [[BR]]
     59
     60Step 7)  Install Base Station Outdoor Unit:  planned/started/completed x/x/10 [[BR]]
     61
     62Step 8)  Complete Wiring at Outdoor Site and to Indoor Equipment Room:  planned/started/completed x/x/10 [[BR]]
     63
     64Step 9)  Install Indoor Equipment Racks and Ground:  planned/started/completed x/x/10 [[BR]]
     65
     66Step 10)  Install 120VAC and -48VDC Power Feeds and/or Supplies:  planned/started/completed x/x/10 [[BR]]
     67
     68Step 11)  Install Base Station Indoor Unit:  planned/started/completed x/x/10 [[BR]]
     69
     70Step 12)  Complete Wiring of Base Station Indoor Unit:  planned/started/completed x/x/10 [[BR]]
     71
     72Step 13)  Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units:  planned/started/completed x/x/10 [[BR]]
     73
     74Step 14)  Install Ethernet (VLAN) Switch, or Identify Existing Capacity:  planned/started/completed x/x/10 [[BR]]
     75
     76Step 15)  Install Linux Server(s) and Software:  planned/started/completed x/x/10 [[BR]]
     77
     78Step 16)  Connect Backbone Network:  planned/started/completed x/x/10 [[BR]]
     79
     80Step 17)  Provide Reference Client Platform:  planned/started/completed x/x/10 [[BR]]
     81
     82Step 18)  Inital Check-Out of Campus WiMAX Testbed:  planned/started/completed x/x/10 [[BR]]
     83
    3784
    3885== Project Technical Documents ==