    5151|| 2 || Obtain FCC License || - || 03/10 || 05/10 || 2 Year License Granted, Additional years if needed will be requested. The license has 2 frequencies 2,572MHz an 2,590MHz. 2 Campus Locations are authorized to transmit.||
    5252|| 3 || Identify Indoor Equipment Room on Campus || - || 04/10 || 06/10 ||2 Locations 1 in Boelter Hall and 1 in Sproul Hall.||
    53 || 4 || Install Wiring at Outdoor Site and to Indoor Equipment Room || - || 06/10 || - ||Indoor Completed. Outdoor completion expected on 9/20- pending Tower Arrival||
     53|| 4 || Install Wiring at Outdoor Site and to Indoor Equipment Room || - || 06/10 || 9/29  ||Wiring Completed, fiber installed.||
    5454|| 5 || Install Pole at Outdoor Site and Ground  || - || 06/10 || - || 10' Must is purchased and Arrived, the 8' tall aluminum tower is ordered but not yet delivered.||
    5555|| 6 || Install Antenna at Outdoor Site  || - || 07/10|| - ||The Roof-Top metal Grid has been installed as well as the mounts. Waiting for tower to finalize. ||