  • WIMXUCLA

    v17 v18  
    4848
    4949|| Step || Description || Planned || Started || Completed || Comment ||
    50 ||   1  || Identify Outdoor Site on Campus || - || Completed  || -|| Identified 2 locations: 1 on the hill: Sproul Hall one of the student housing building; the second one on Boelter Hall CSD. Initial Setup on Boelter Hall for Testing purposes. The WiFi sites are 6 and they cover the whole campus; topology posted as picture below. ||
    51 || 2 || Obtain FCC License || - || Completed || - || 2 Year License Granted, Additional years if needed will be requested. The license has 2 frequencies 2,572MHz an 2,590MHz. 2 Campus Locations are authorized to transmit.||
    52 || 3 || Identify Indoor Equipment Room on Campus || - || Completed || - ||2 Locations 1 in Boelter Hall and 1 in Sproul Hall.||
    53 || 4 || Install Wiring at Outdoor Site and to Indoor Equipment Room || - || Started || - ||Indoor Completed. Outdoor completion expected on 9/20- pending Tower Arrival||
    54 || 5 || Install Pole at Outdoor Site and Ground  || - || Started || - || Must is purchased, the 8' tall aluminum tower is ordered but not yet delivered.||
    55 || 6 || Install Antenna at Outdoor Site  || - || Started|| - ||The Roof-Top metal Grid has been installed as well as the mounts. Waiting for tower to finalize. ||
    56 || 7 || Install Base Station Outdoor Unit  || - || Started || - ||Infrastructure work done. Cable wiring on way. ||
    57 || 8 || Complete Wiring at Outdoor Site and to Indoor Equipment Room  || - || Started || - ||Indoor is finalized, outdoor is on hold for missing parts expected anytime now. ||
    58 || 9 || Install Indoor Equipment Racks and Ground  || - || Started || - ||Rack has not yet been received is expected in September.||
    59 || 10 || Install 120VAC and -48VDC Power Feeds and/or Supplies  || - || Started || - ||We opted for bringing up the -48VDC power, purchase of water proof cable and connectors has been made delivery is expected on 9/8/2010. ||
     50||   1  || Identify Outdoor Site on Campus || - || 03/10  || 04/10|| Identified 2 locations: 1 on the hill: Sproul Hall one of the student housing building; the second one on Boelter Hall CSD. Initial Setup on Boelter Hall for Testing purposes. The WiFi sites are 6 and they cover the whole campus; topology posted as picture below. ||
     51|| 2 || Obtain FCC License || - || 03/10 || 05/10 || 2 Year License Granted, Additional years if needed will be requested. The license has 2 frequencies 2,572MHz an 2,590MHz. 2 Campus Locations are authorized to transmit.||
     52|| 3 || Identify Indoor Equipment Room on Campus || - || 04/10 || 06/10 ||2 Locations 1 in Boelter Hall and 1 in Sproul Hall.||
     53|| 4 || Install Wiring at Outdoor Site and to Indoor Equipment Room || - || 06/10 || - ||Indoor Completed. Outdoor completion expected on 9/20- pending Tower Arrival||
     54|| 5 || Install Pole at Outdoor Site and Ground  || - || 06/10 || - || 10' Must is purchased and Arrived, the 8' tall aluminum tower is ordered but not yet delivered.||
     55|| 6 || Install Antenna at Outdoor Site  || - || 07/10|| - ||The Roof-Top metal Grid has been installed as well as the mounts. Waiting for tower to finalize. ||
     56|| 7 || Install Base Station Outdoor Unit  || - || 07/10 || - ||Infrastructure work done. Cable wiring on way. ||
     57|| 8 || Complete Wiring at Outdoor Site and to Indoor Equipment Room  || - || 08/10 || - ||Indoor is finalized, outdoor is on hold for missing parts expected anytime now. ||
     58|| 9 || Install Indoor Equipment Racks and Ground  || - || - || - ||Rack has not yet been received is expected in September.||
     59|| 10 || Install 120VAC and -48VDC Power Feeds and/or Supplies  || - || 08/10 || - ||We opted for bringing up the -48VDC power, purchase of water proof cable and connectors has been made delivery is expected on 9/8/2010. ||
    6060|| 11 || Install Base Station Indoor Unit  || - || - || - || ||
    6161|| 12 || Complete Wiring of Base Station Indoor Unit  || - || - || - || ||
    6262|| 13 || Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units  || - || - || - || ||
    63 || 14 || Install Ethernet (VLAN) Switch, or Identify Existing Capacity  || - || - || - || ||
    64 || 15 || Install Linux Server(s) and Software || - || Started || - ||WiFi MESH control center and network management is up and runnng. OMF Server is up and running. OMF 5.3 is running a testing server. ||
    65 || 16 || Connect Backbone Network  || - || - || - || ||
     63|| 14 || Install Ethernet (VLAN) Switch, or Identify Existing Capacity  || - || 07/10 || - ||Switch has been ordered. ||
     64|| 15 || Install Linux Server(s) and Software || - || 04/10 || - ||WiFi MESH control center and network management is up and runnng. OMF Server is up and running. OMF 5.3 is running a testing server. ||
     65|| 16 || Connect Backbone Network  || - || 07/10 || - || Connection to Campus Network Granted through standard 1GB/S line and I2 POP, ION interface planned but not active yet. ||
    6666|| 17 || Provide Reference Client Platform  || - || - || - || ||
    6767|| 18 || Initial Check-Out of Campus WiMAX Testbed  || - || - || - || ||