Version 17 (modified by 15 years ago) (diff) | ,
---|
Project Number
1751
Project Title
Campus deployment of an open GENI WiMAX 802.16e Testbed in Polytechnic Institute of NYU
a.k.a WIMXNYUPT
Technical Contacts
PI: Thanasis Korakis korakis@poly.edu
Participating Organizations
Polytechnic University of NYU, Brooklyn, NY
GPO Liaison System Engineer
Harry Mussman hmussman@geni.net
Scope
This project builds an open/programmable WiMax testbed on the campus of Polytechnic University of NYU. It utilizes the "Open GENI WiMax Base Station Kit for Campus Deployments" provided by an associated project (Rutgers and NEC). It provides for the installation, maintenance and integration of the WiMax base station kit with existing experimentation facilities at the university.
Current Capabilities
Milestones
MilestoneDate(WIMXNYUPT: S2.a Complete Installation)?
MilestoneDate(WIMXNYUPT: S2.b Multi-campus Demo)?
Campus Installation Checklist
Polytechnic University of NYU
Contact(s):
PI: Thanasis Korakis korakis@poly.edu
Step | Description | Planned | Started | Completed | Comment |
1 | Identify Outdoor Site on Campus | - | Started | - | Likely site on ECE building |
2 | Obtain FCC License | - | Started | - | |
3 | Identify Indoor Equipment Room on Campus | - | Started | - | The Witest Lab in the ECE building |
4 | Install Wiring at Outdoor Site and to Indoor Equipment Room | - | - | - | |
5 | Install Pole at Outdoor Site and Ground | - | - | - | |
6 | Install Antenna at Outdoor Site | - | - | - | |
7 | Install Base Station Outdoor Unit | - | - | - | |
8 | Complete Wiring at Outdoor Site and to Indoor Equipment Room | - | - | - | |
9 | Install Indoor Equipment Racks and Ground | - | - | - | |
10 | Install 120VAC and -48VDC Power Feeds and/or Supplies | - | - | - | |
11 | Install Base Station Indoor Unit | - | - | - | |
12 | Complete Wiring of Base Station Indoor Unit | - | - | - | |
13 | Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units | - | - | - | |
14 | Install Ethernet (VLAN) Switch, or Identify Existing Capacity | - | - | - | |
15 | Install Linux Server(s) and Software | - | - | - | |
16 | Connect Backbone Network | - | - | - | |
17 | Provide Reference Client Platform | - | - | - | |
18 | Initial Check-Out of Campus WiMAX Testbed | - | - | - |
Project Technical Documents
Quarterly Status Reports
Spiral 2 Connectivity
Related Projects
Attachments (1)
- GENI_WiMAX_Poly_review_Sept_2010.pdf (449.5 KB) - added by 14 years ago.
Download all attachments as: .zip