46 | | || 1 || Identify Outdoor Site on Campus || - || Started || -|| Likely site on ECE building || |
47 | | || 2 || Obtain FCC License || - || Started || - || || |
48 | | || 3 || Identify Indoor Equipment Room on Campus || - || Started || - || The Witest Lab in the ECE building || |
49 | | || 4 || Install Wiring at Outdoor Site and to Indoor Equipment Room || - || - || - || || |
50 | | || 5 || Install Pole at Outdoor Site and Ground || - || - || - || || |
51 | | || 6 || Install Antenna at Outdoor Site || - || - || - || || |
52 | | || 7 || Install Base Station Outdoor Unit || - || - || - || || |
53 | | || 8 || Complete Wiring at Outdoor Site and to Indoor Equipment Room || - || - || - || || |
54 | | || 9 || Install Indoor Equipment Racks and Ground || - || - || - || || |
55 | | || 10 || Install 120VAC and -48VDC Power Feeds and/or Supplies || - || - || - || || |
56 | | || 11 || Install Base Station Indoor Unit || - || - || - || || |
57 | | || 12 || Complete Wiring of Base Station Indoor Unit || - || - || - || || |
58 | | || 13 || Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units || - || - || - || || |
59 | | || 14 || Install Ethernet (VLAN) Switch, or Identify Existing Capacity || - || - || - || || |
60 | | || 15 || Install Linux Server(s) and Software || - || - || - || || |
61 | | || 16 || Connect Backbone Network || - || - || - || || |
62 | | || 17 || Provide Reference Client Platform || - || - || - || || |
63 | | || 18 || Initial Check-Out of Campus WiMAX Testbed || - || - || - || || |
| 46 | || 1 || Identify Outdoor Site on Campus || - || Started || Completed || Roof of the ECE building || |
| 47 | || 2 || Obtain FCC License || - || Started || Completed || || |
| 48 | || 3 || Identify Indoor Equipment Room on Campus || - || Started || Completed || Networking room of the Library in the ECE building || |
| 49 | || 4 || Install Wiring at Outdoor Site and to Indoor Equipment Room || - || Started || Completed || || |
| 50 | || 5 || Install Pole at Outdoor Site and Ground || - || Started || Completed || || |
| 51 | || 6 || Install Antenna at Outdoor Site || - || Started || Completed || || |
| 52 | || 7 || Install Base Station Outdoor Unit || - || Started || Completed || || |
| 53 | || 8 || Complete Wiring at Outdoor Site and to Indoor Equipment Room || - || Started || Completed || || |
| 54 | || 9 || Install Indoor Equipment Racks and Ground || - || Started || Completed || || |
| 55 | || 10 || Install 120VAC and -48VDC Power Feeds and/or Supplies || - || Started || Completed || || |
| 56 | || 11 || Install Base Station Indoor Unit || - || Started || Completed || || |
| 57 | || 12 || Complete Wiring of Base Station Indoor Unit || - || Started || Completed || || |
| 58 | || 13 || Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units || - ||Started || Completed || || |
| 59 | || 14 || Install Ethernet (VLAN) Switch, or Identify Existing Capacity || - || Started || Completed || || |
| 60 | || 15 || Install Linux Server(s) and Software || - || Started || Completed || || |
| 61 | || 16 || Connect Backbone Network || - || Started || Completed || || |
| 62 | || 17 || Provide Reference Client Platform || - || Started || Completed || || |
| 63 | || 18 || Initial Check-Out of Campus WiMAX Testbed || - || Started || Completed || || |