wiki:WIMXCOLUM

Version 6 (modified by hmussman@bbn.com, 14 years ago) (diff)

--

Project Number

1770

Project Title

GENI WiMax Base Station Kit - Columbia University Deployment
a.k.a WIMXCOLUM

Technical Contacts

PI: Henning Schulzrinne hgs@cs.columbia.edu

Participating Organizations

Columbia University CS Dept, New York, NY

GPO Liaison System Engineer

Harry Mussman hmussman@geni.net

Scope

This project will install a GENI WiMax Base Station Kit provided by Rutgers on the Columbia University campus, and operate it with the ORBIT Management Framework (OMF). It will enhance our WORKIT nodes with WiMax clients and GPS capabilities, add remote control and virtualization capabilities, and operate them with OMF. It will also build teaching modules to explore wide area wireless network issues and applications.

Current Capabilities

Milestones

MilestoneDate(WIMXCOLUM: S2.a Prepare site)?
MilestoneDate(WIMXCOLUM: S2.b Start software for WORKIT nodes)?
MilestoneDate(WIMXCOLUM: S2.c Begin teaching modules)?

Campus Installation Checklist

Columbia University

Contact(s):
PI: Henning Schulzrinne hgs@cs.columbia.edu

Step 1) Identify Outdoor Site on Campus: planned/started/completed x/x/10

Step 2) Obtain FCC License: planned/started/completed x/x/10

Step 3) Identify Indoor Equipment Room on Campus: planned/started/completed x/x/10

Step 4) Install Wiring at Outdoor Site and to Indoor Equipment Room: planned/started/completed x/x/10

Step 5) Install Pole at Outdoor Site and Ground: planned/started/completed x/x/10

Step 6) Install Antenna at Outdoor Site: planned/started/completed x/x/10

Step 7) Install Base Station Outdoor Unit: planned/started/completed x/x/10

Step 8) Complete Wiring at Outdoor Site and to Indoor Equipment Room: planned/started/completed x/x/10

Step 9) Install Indoor Equipment Racks and Ground: planned/started/completed x/x/10

Step 10) Install 120VAC and -48VDC Power Feeds and/or Supplies: planned/started/completed x/x/10

Step 11) Install Base Station Indoor Unit: planned/started/completed x/x/10

Step 12) Complete Wiring of Base Station Indoor Unit: planned/started/completed x/x/10

Step 13) Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units: planned/started/completed x/x/10

Step 14) Install Ethernet (VLAN) Switch, or Identify Existing Capacity: planned/started/completed x/x/10

Step 15) Install Linux Server(s) and Software: planned/started/completed x/x/10

Step 16) Connect Backbone Network: planned/started/completed x/x/10

Step 17) Provide Reference Client Platform: planned/started/completed x/x/10

Step 18) Inital Check-Out of Campus WiMAX Testbed: planned/started/completed x/x/10

Project Technical Documents

Quarterly Status Reports

Spiral 2 Connectivity

Related Projects

Open GENI WiMAX Base Station Kit for Campus Deployments

Attachments (1)