Project Number
1770
Project Title
GENI WiMax Base Station Kit - Columbia University Deployment
a.k.a WIMXCOLUM
Technical Contacts
PI: Henning Schulzrinne hgs@cs.columbia.edu
Participating Organizations
Columbia University CS Dept, New York, NY
GPO Liaison System Engineer
Harry Mussman hmussman@geni.net
Scope
This project will install a GENI WiMax Base Station Kit provided by Rutgers on the Columbia University campus, and operate it with the ORBIT Management Framework (OMF). It will enhance our WORKIT nodes with WiMax clients and GPS capabilities, add remote control and virtualization capabilities, and operate them with OMF. It will also build teaching modules to explore wide area wireless network issues and applications.
Current Capabilities
Milestones
MilestoneDate(WIMXCOLUM: S2.a Prepare site)?
MilestoneDate(WIMXCOLUM: S2.b Start software for WORKIT nodes)?
MilestoneDate(WIMXCOLUM: S2.c Begin teaching modules)?
Campus Installation Checklist
Columbia University
Contact(s):
PI: Henning Schulzrinne hgs@cs.columbia.edu
Step | Description | Planned | Started | Completed | Comment |
1 | Identify Outdoor Site on Campus | - | Started | - | Likely site to be on engineering building, near amateur radio station |
2 | Obtain FCC License | - | Started | - | |
3 | Identify Indoor Equipment Room on Campus | - | - | - | |
4 | Install Wiring at Outdoor Site and to Indoor Equipment Room | - | - | - | |
5 | Install Pole at Outdoor Site and Ground | - | - | - | |
6 | Install Antenna at Outdoor Site | - | - | - | |
7 | Install Base Station Outdoor Unit | - | - | - | |
8 | Complete Wiring at Outdoor Site and to Indoor Equipment Room | - | - | - | |
9 | Install Indoor Equipment Racks and Ground | - | - | - | |
10 | Install 120VAC and -48VDC Power Feeds and/or Supplies | - | - | - | |
11 | Install Base Station Indoor Unit | - | - | - | |
12 | Complete Wiring of Base Station Indoor Unit | - | - | - | |
13 | Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units | - | - | - | |
14 | Install Ethernet (VLAN) Switch, or Identify Existing Capacity | - | - | - | |
15 | Install Linux Server(s) and Software | - | - | - | |
16 | Connect Backbone Network | - | - | - | |
17 | Provide Reference Client Platform | - | - | - | |
18 | Initial Check-Out of Campus WiMAX Testbed | - | - | - |
Project Technical Documents
Quarterly Status Reports
Spiral 2 Connectivity
Related Projects
Attachments (1)
- Columbia modified geni_wimax.ppt (256.0 KB) - added by 14 years ago.
Download all attachments as: .zip