  • WIMXBBN

    v6 v7  
    4747
    4848
    49 Step 1)  Identify Outdoor Site on Campus:    Completed 1/10;  roof of BBN building at 10 Moulton, Cambridge;  near other antennas;  brackets on building to mount pole for antenna and pole;  thick ground wire available;  conduit for entry through roof available, used for other antenna cables;  can drop fiber and -48VDC power cables through conduit, down to 5th floor, and over to testbed, estimate 150ft +-.  TM [[BR]]
     49Step 1)  Identify Outdoor Site on Campus:    Completed 1/10 TM;  roof of BBN Technologies building at 10 Moulton, Cambridge;  near other antennas;  brackets on building to mount pole for antenna and pole;  thick ground wire available and in use for other antennas;  conduit for entry through roof available, in use for other antenna cables;  can drop fiber and -48VDC power cables through conduit, down to 5th floor, and over to testbed, estimated 150ft+.  [[BR]]
    5050
    51 Step 2)  Obtain FCC License:  A)  Applied 10MHz overlapping Sprint;  started 12/09;  pending;  B) Applied 5MHz between Northeastern bands; started 1/10;  pending;  both)  Received call sign (Wxxxx) on 1/10  TM   [[BR]]
     51Step 2)  Obtain FCC License:  A)  Applied 10MHz overlapping Sprint;  started 12/09 TM;  pending;  B) Applied 5MHz between Northeastern bands; started 1/10 TM;  pending;  both)  Received call sign (Wxxxx) on 1/10  TM   [[BR]]
    5252
    5353Step 3)  Identify Indoor Equipment Room on Campus:  Completed 7/09  CG [[BR]]