    4949|| Step || Description || Planned || Started || Completed || Comment ||
    50 ||   1  || Identify Outdoor Site on Campus || 1/10 || 1/10  || 1/10 || roof of BBN Technologies building at 10 Moulton, Cambridge;  near other antennas;  brackets on building to mount pole for antenna and pole;  thick ground wire available and in use for other antennas;  conduit for entry through roof available, in use for other antenna cables;  can drop fiber and -48VDC power cables through conduit, down to 5th floor, and over to testbed, estimated 150ft+. ||
    51 || 2a || Obtain FCC License || 12/09 || 12/09 || - || Applied for 10MHz overlapping Sprint ||
    52 || 2b || Obtain FCC License || 1/10 || 1/10 || - || Applied for 5MHz between Northeastern bands ||
    53 || 3 || Identify Indoor Equipment Room on Campus || 7/09 || 7/09 || 7/09 || CG;  room 6/523 at 10 Moulton.||
     50||   1  || Identify Outdoor Site on Campus || 1/10 || 1/10  || 1/10 || TM:  roof of BBN Technologies building at 10 Moulton, Cambridge;  near other antennas;  brackets on building to mount pole for antenna and pole;  thick ground wire available and in use for other antennas;  conduit for entry through roof available, in use for other antenna cables;  can drop fiber and -48VDC power cables through conduit, down to 5th floor, and over to testbed, estimated 150ft+. ||
     51|| 2a || Obtain FCC License || 12/09 || 12/09 || - || TM:  Applied for 10MHz overlapping Sprint ||
     52|| 2b || Obtain FCC License || 1/10 || 1/10 || - || TM:  Applied for 5MHz between Northeastern bands ||
     53|| 3 || Identify Indoor Equipment Room on Campus || 7/09 || 7/09 || 7/09 || CG:  room 6/523 at 10 Moulton.||
    5454|| 4 || Install Wiring at Outdoor Site and to Indoor Equipment Room || - || - || - || ||
    5555|| 5 || Install Pole at Outdoor Site and Ground  || - || - || - || ||