49 | | Step 1) Identify Outdoor Site on Campus: Completed 1/10 TM; roof of BBN Technologies building at 10 Moulton, Cambridge; near other antennas; brackets on building to mount pole for antenna and pole; thick ground wire available and in use for other antennas; conduit for entry through roof available, in use for other antenna cables; can drop fiber and -48VDC power cables through conduit, down to 5th floor, and over to testbed, estimated 150ft+. [[BR]] |
50 | | |
51 | | Step 2) Obtain FCC License: A) Applied 10MHz overlapping Sprint; started 12/09 TM; pending; B) Applied 5MHz between Northeastern bands; started 1/10 TM; pending; both) Received call sign (Wxxxx) on 1/10 TM [[BR]] |
52 | | |
53 | | Step 3) Identify Indoor Equipment Room on Campus: Completed 7/09 CG; room 6/523 at 10 Moulton. [[BR]] |
54 | | |
55 | | Step 4) Install Wiring at Outdoor Site and to Indoor Equipment Room: planned/started/completed x/x/10 [[BR]] |
56 | | |
57 | | Step 5) Install Pole at Outdoor Site and Ground: planned/started/completed x/x/10 [[BR]] |
58 | | |
59 | | Step 6) Install Antenna at Outdoor Site: planned/started/completed x/x/10 [[BR]] |
60 | | |
61 | | Step 7) Install Base Station Outdoor Unit: planned/started/completed x/x/10 [[BR]] |
62 | | |
63 | | Step 8) Complete Wiring at Outdoor Site and to Indoor Equipment Room: planned/started/completed x/x/10 [[BR]] |
64 | | |
65 | | Step 9) Install Indoor Equipment Racks and Ground: planned/started/completed x/x/10 [[BR]] |
66 | | |
67 | | Step 10) Install 120VAC and -48VDC Power Feeds and/or Supplies: planned/started/completed x/x/10 [[BR]] |
68 | | |
69 | | Step 11) Install Base Station Indoor Unit: planned/started/completed x/x/10 [[BR]] |
70 | | |
71 | | Step 12) Complete Wiring of Base Station Indoor Unit: planned/started/completed x/x/10 [[BR]] |
72 | | |
73 | | Step 13) Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units: planned/started/completed x/x/10 [[BR]] |
74 | | |
75 | | Step 14) Install Ethernet (VLAN) Switch, or Identify Existing Capacity: planned/started/completed x/x/10 [[BR]] |
76 | | |
77 | | Step 15) Install Linux Server(s) and Software: planned/started/completed x/x/10 [[BR]] |
78 | | |
79 | | Step 16) Connect Backbone Network: planned/started/completed x/x/10 [[BR]] |
80 | | |
81 | | Step 17) Provide Reference Client Platform: planned/started/completed x/x/10 [[BR]] |
82 | | |
83 | | Step 18) Inital Check-Out of Campus WiMAX Testbed: planned/started/completed x/x/10 [[BR]] |
| 49 | || Step || Description || Planned || Started || Completed || Comment || |
| 50 | || 1 || Identify Outdoor Site on Campus || 1/10 || 1/10 || 1/10 || roof of BBN Technologies building at 10 Moulton, Cambridge; near other antennas; brackets on building to mount pole for antenna and pole; thick ground wire available and in use for other antennas; conduit for entry through roof available, in use for other antenna cables; can drop fiber and -48VDC power cables through conduit, down to 5th floor, and over to testbed, estimated 150ft+. || |
| 51 | || 2a || Obtain FCC License || 12/09 || 12/09 || - || Applied for 10MHz overlapping Sprint || |
| 52 | || 2b || Obtain FCC License || 1/10 || 1/10 || - || Applied for 5MHz between Northeastern bands || |
| 53 | || 3 || Identify Indoor Equipment Room on Campus || 7/09 || 7/09 || 7/09 || CG; room 6/523 at 10 Moulton.|| |
| 54 | || 4 || Install Wiring at Outdoor Site and to Indoor Equipment Room || - || - || - || || |
| 55 | || 5 || Install Pole at Outdoor Site and Ground || - || - || - || || |
| 56 | || 6 || Install Antenna at Outdoor Site || - || - || - || || |
| 57 | || 7 || Install Base Station Outdoor Unit || - || - || - || || |
| 58 | || 8 || Complete Wiring at Outdoor Site and to Indoor Equipment Room || - || - || - || || |
| 59 | || 9 || Install Indoor Equipment Racks and Ground || - || - || - || || |
| 60 | || 10 || Install 120VAC and -48VDC Power Feeds and/or Supplies || - || - || - || || |
| 61 | || 11 || Install Base Station Indoor Unit || - || - || - || || |
| 62 | || 12 || Complete Wiring of Base Station Indoor Unit || - || - || - || || |
| 63 | || 13 || Initial Check-Out of Antenna and Base Station Outdoor and Indoor Units || - || - || - || || |
| 64 | || 14 || Install Ethernet (VLAN) Switch, or Identify Existing Capacity || - || - || - || || |
| 65 | || 15 || Install Linux Server(s) and Software || - || - || - || || |
| 66 | || 16 || Connect Backbone Network || - || - || - || || |
| 67 | || 17 || Provide Reference Client Platform || - || - || - || || |
| 68 | || 18 || Initial Check-Out of Campus WiMAX Testbed || - || - || - || || |