  • ViSE

    v35 v36  
    5656[milestone:"ViSE: 1a Assembly of three x86 sensor nodes"]
    5757due 12/1/08
    58 [  "completed 12/5/08"]
     58[  "completed 12/5/08"][[BR]]
     59[milestone:"ViSE: 1b Field deployment of three sensor nodes"]
     60due 1/1/09
     61[  "completed 12/30/08"][[BR]]
     62[milestone:"ViSE: 1c Initial Shirako/ORCA integration-"]
     63due 2/1/09
     64[  "completed 2/2/09][[BR]]
     65[milestone:"ViSE: 1d Operational web portal and testbed; Application demo"]
     66due 4/1/09
     67[  "completed 3/31/09][[BR]]
     68[milestone:"ViSE: 1c2 Complete initial Shirako/ORCA integration-"]
     69due 4/30/09
     70[  "completed 5/1/09][[BR]]
     71[milestone:"ViSE: 1e Contingent upon availability of reference implementation of Shirako/ORCA at 6 months, import and then integrate"]
     72due 8/1/09
     73[  "started"[[BR]]
     74[milestone:"ViSE: 1f Complete Xen sensor virtualization"]
     75due 8/1/09
     76[  "started"][[BR]]
     77[milestone:"ViSE: 1g Contingent upon available budget, provide a VLAN connection from your testbed to the Internet2"]
     78due 10/1/09
    5979[[BR]]
    60 [milestone:"ViSE: 1b Field deployment of three sensor nodes"]  [[BR]]
    61 [milestone:"ViSE: 1c Initial Shirako/ORCA integration-"]  [[BR]]
    62 [milestone:"ViSE: 1d Operational web portal and testbed; Application demo"]  [[BR]]
    63 [milestone:"ViSE: 1c2 Complete initial Shirako/ORCA integration-"]  [[BR]]
    64 [milestone:"ViSE: 1e Contingent upon availability of reference implementation of Shirako/ORCA at 6 months, import and then integrate"][[BR]]
    65 [milestone:"ViSE: 1f Complete Xen sensor virtualization"][[BR]]
    66 [milestone:"ViSE: 1g Contingent upon available budget, provide a VLAN connection from your testbed to the Internet2"][[BR]]
    67 [milestone:"ViSE: 1h Virtualization of actuators; single guest VM; demo"]  [[BR]]
    68 [milestone:"ViSE: 1i Testbed available for public use within our cluster"]  [[BR]]
     80[milestone:"ViSE: 1h Virtualization of actuators; single guest VM; demo"]
     81due 10/1/09[[BR]]
     82[milestone:"ViSE: 1i Testbed available for public use within our cluster"]
     83due 10/1/09[[BR]]
    6984