34 | | || Acquire and test HP aggregate switch for ProtoGENI and first GENI rack || Complete || April || June 15 || First rack is Rob's InstaGENI rack || |
35 | | || Deploy aggregate switch and bring new connections to Univ of Utah and UEN || || June 15 || July 6 || Dependent on testing of InstaGENI rack because implementation involves interruption of current ProtoGENI infrastructure || |
| 34 | || Acquire and test HP aggregate switch for ProtoGENI and first GENI rack || Complete || April 2012 || June 15, 2012 || First rack is Rob's InstaGENI rack || |
| 35 | || Deploy aggregate switch and bring new connections to Univ of Utah and UEN || || June 15, 2012 || July 6, 2012 || Dependent on testing of InstaGENI rack because implementation involves interruption of current ProtoGENI infrastructure || |