    3131== Milestones ==
    3232
     33|| '''Milestone''' || '''Status''' || '''Begin Date''' || '''End Date''' || '''Notes''' ||
     34|| Acquire and test HP aggregate switch for ProtoGENI and first GENI rack || Complete || April || June 15 || First rack is Rob's InstaGENI rack ||
     35|| Deploy aggregate switch and bring new connections to Univ of Utah and UEN || || June 15 || July 6 || Dependent on testing of InstaGENI rack because implementation involves interruption of current ProtoGENI infrastructure ||
     36|| Support multi-campus demo that includes new resources from this deployment and existing meso-scale resources. (GEC July, 2012 || || July 8, 2012 ||  ||
     37|| Integrate and test with other existing Internet2 and NLR OpenFlow meso-scale deployments and GENI racks. (August 30, 2012) || || || Aug 30, 2012 || ||
     38|| Make Switch resources available to NSF experimenters || || || Sept 30, 2012 || ||
     39|| Acquire and test HP switch and second GENI rack || || 2013 || ||
     40|| Connect UEN data center and second GENI rack to regional OpenFlow network || || || 2013 || ||
     41|| Transition stable parts of network to operations and support experimenters || || || 2013 || ||
     42|| Acquire 2 HP Procurve 6600 switches and supporting equipment || || || 2014 || ||
     43|| Connect 2 additional GENI racks in UEN to regional OpenFlow network || || || 2014 || ||
     44|| Transition to operations || || || 2014 || ||