37 | | || Deploy aggregate switch and bring new connections to Univ of Utah and UEN || Complete || June 15, 2012 || July 6, 2012 || Dependent on testing of InstaGENI rack because implementation involves interruption of current ProtoGENI infrastructure || |
38 | | || Support multi-campus demo that includes new resources from this deployment and existing meso-scale resources. (GEC July, 2012) || || July 8, 2012 || || |
39 | | || Integrate and test with other existing Internet2 and NLR OpenFlow meso-scale deployments and GENI racks. (August 30, 2012) || || || Aug 30, 2012 || || |
40 | | || Make Switch resources available to NSF experimenters || || || Sept 30, 2012 || || |
| 37 | || Deploy aggregate switch and bring new connections to Univ of Utah and UEN || Complete || June 15, 2012 || July 6, 2012 || Dependent on testing of InstaGENI rack because implementation - involves interruption of current ProtoGENI infrastructure || |
| 38 | || Support multi-campus demo that includes new resources from this deployment and existing meso-scale resources. (GEC July, 2012) || Complete || July 1, 2012 || Aug 22, 2012 || Did not use UEN aggregate switch - Used only ProtoGENI direct connection into the GENI backbone. Could not interrupt the experiments for the data plane cutover || |
| 39 | || Integrate and test with other existing Internet2 and NLR OpenFlow meso-scale deployments and GENI racks. (August 30, 2012) || || Sept 23, 2012 || Sept 30, 2012 || || |
| 40 | || Make Switch resources available to NSF experimenters || || Sept 23, 2012 || Sept 30, 2012 || || |