     1== ''***GENI PLANNING GROUP DOCUMENTS ARE NO LONGER CURRENT.  See GpoDoc and the GENI project pages for up-to-date documents and specifications.***'' ==
     2
     3== Schedule ==
     4
     5The following is the rough timetable for further development of GENI's research plan, reference design, and execution plan, in preparation for a Conceptual Design Review (CDR) in early 2007.
     6November 1st: 2nd draft of GDDs
     7
     8    * complete draft of research plan by 11/21
     9
     10December 1st: 3rd draft of GDDs
     11January 1st: Penultimate draft of GDDs (including research plan)
     12
     13    * Activities in January:
     14          * integrate design/wbs/budget (extracted from GDDs) into PEP
     15          * review of research plan (organized by CCC)
     16
     17February 1st: Penultimate draft of PEP and Research Plan
     18
     19    * Activities in February:
     20          * GDDs revised to be consistent with PEP
     21          * planning group brings GPO up-to-speed
     22
     23March 1st: Final version of PEP, Research Plan, supporting GDDs
     24
     25    * documents frozen for review
     26
     27April 1st: Conceptual Design Review (CDR)
     28May 1st: GENI presented to NSB
     29
     30Assuming GENI passes the CDR and is inserted into the Readiness Queue, the post-CDR timeline for the the MREFC process looks like this:
     31
     32[[Image(post_cdr_mrefc_timeline.jpg)]]