= OFNLR Project Status Report = == Period: 2010-Q2 == This project will deploy and operate OpenFlow-enabled HP Procurve 6600 switches at 5 NLR PoPs and interconnect NLR’s FrameNet network to the GENI OpenFlow-enabled backbone, permitting members and non-members of NLR to connect to GENI OpenFlow services.[[BR]] === I. Major accomplishments''' === '''A. Milestones achieved'''[[BR]] Currently in process: * OFNLR: S2.b Lab test OpenFlow 1.0 capable switch and controller * OFNLR: S2.c Deploy OpenFlow switches to five POPs * OFNLR: S2.d Engineer and test regional network connections '''B. Deliverables made'''[[BR]] * Equipment installation planning completed * Switches and supporting components acquired * Switches deployed to 4 of the 5 PoP locations === II. Description of work performed during last quarter === '''A. Activities and findings'''[[BR]] * Equipment planning and installation * Verified availability of rack space, AC power, and cooling in each of the designated PoPs * Generated optical engineering design and verified available optical wavelength and slotting capacity throughout the Layer 1 WaveNet path * Confirmed availability of Layer 2 FrameNet ports and optics and out-of-band ports * Generated installation and cross-connect orders * Switches installed in Atlanta, Sunnyvale, Seattle, and Chicago * Switch and system components ordering * Selected HP 6600-24G-4XG switch * Used the information from the “Equipment planning and installation” activity to generate component purchase list * Placed orders for all equipment * OpenFlow controller installed and tested based on OpenFlow 1.0 * Planning for GEC8 demo '''B. Project participants'''[[BR]] * PI: Glenn Ricart, NLR CEO * Grover Browning, NLR Director of Engineering and Operations * Andrew Lee, Network Engineer * Ron Milford, Network Engineer * Chris Small, Systems Engineer * Kathy Benninger, Project Manager '''C. Publications (individual and organizational)''' [[BR]] '''D. Outreach activities'''[[BR]] '''E. Collaborations'''[[BR]] * GPO/Stanford/IU collaboration and discussion led to: * Choosing an OpenFlow-enabled switch with primarily 1GbE ports for direct connections * Adding Layer 2 FrameNet connections to all OpenFlow switches * GPO/Internet2 * NLR Internet 2 backbone connection planning in Atlanta '''F. Other Contributions'''[[BR]]