Changes between Version 9 and Version 10 of OFI2


Ignore:
Timestamp:
02/08/11 14:36:48 (13 years ago)
Author:
jmccolga@bbn.com
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • OFI2

    v9 v10  
    4242[[MilestoneDate(OFI2: S2.f Provide access to OpenFlow slivers for testing)]] [[BR]]
    4343[[MilestoneDate(OFI2: S2.g Plan and engineer GEC 9 demo)]] [[BR]]
     44
     45[[MilestoneDate(OFI2: S3.a.1 Complete end-to-end OpenFlow tests between existing Spiral2 OpenFlow campuses that want to participate in testing)]] [[BR]]
     46[[MilestoneDate(OFI2: S3.a.2 Support new and existing OpenFlow sites)]] [[BR]]
     47[[MilestoneDate(OFI2: S3.b.1 "Initial integration with AM, NLR, campuses and other aggregates")]] [[BR]]
     48[[MilestoneDate(OFI2: S3.b.2 "Second integration with AM, NLR, campuses and other aggregates")]] [[BR]]
     49[[MilestoneDate(OFI2: S3.c.1 Complete documentation and procedures for operations support)]] [[BR]]
     50[[MilestoneDate(OFI2: S3.c.2 Implement procedures for operations support)]] [[BR]]
     51[[MilestoneDate(OFI2: S3.d Support multi-site GENI experiments)]] [[BR]]
     52[[MilestoneDate(OFI2: S3.e Complete engineering plan for new I2 10Gbps and existing 1Gbps GENI connections)]] [[BR]]
     53[[MilestoneDate(OFI2: S3.f Install and test 10 Gbps interfaces at Juniper routers to GENI equipment in 4 Internet2 router PoPs)]] [[BR]]
     54[[MilestoneDate(OFI2: S3.g Install and test 4 additional 10 Gbps interfaces on Juniper routers to GENI equipment in Internet2 router PoPs)]] [[BR]]
     55
    4456
    4557== Project Technical Documents ==