  • MAXREGIONAL-GENI-Final-Status-Report

    v2 v3  
    88
    99==  I. Major accomplishments ==
    10 This project no cost extension phase was from October 1, 2014 thru February 15, 2015.   The no cost extension milestones status is provided below.  The milestone status from the previous budget period for this project is also provided below.
     10This project no cost extension phase was from October 1, 2014 thru February 15, 2015.   The no cost extension activity status is provided below.  The milestone status from the previous budget period for this project is also provided below.
    1111
    1212=== A. Milestones status ===