OpenGENI New Site Confirmation Test Status
This page captures the status for new OpenGENI sites that are validated by the GPO upon completion of the GENI Rack Site Installation Check List. The GPO executes Administration, Experiment and Monitoring tests to confirm the ability of a New Site to operate within the GENI environment. Tests are defined in the OpenGENI New Site Confirmation Tests page.
Site Status
Undergoing Confirmation Tests:
Completed Confirmation Tests successfully:
Status Legend
Overall OpenGENI Site Status may be one of the following:
- Pass - Site confirmation tests completed successfully and site is ready for Experimenters.
- Pass: most criteria - Site partially confirmed with documented exceptions.
- Blocked - Site confirmation tests blocked by tracked issue.
- In Progress - Site confirmation tests in progress.
Individual Confirmation Test Status status may be one of the following:
- Color(green,Pass)? - Site Confirmation Test completed and met all criteria
- Color(#98FB98,Pass: most criteria)? - Site Confirmation Test completed and met most criteria with exceptions documented
- Color(red,Fail)? - Site Confirmation Test completed and failed.
- Color(orange,Blocked)? - Site Confirmation Blocked by ticketed issues.
- Color(#63B8FF,In Progress)? - Site Confirmation Test in progress.
OpenGENI Racks Sites Detailed List
Clemson University
Overall Site Status:_ <<insert_site_status>>
Confirmation Test Start Date: 2014-09-17
Confirmation Test Completion Date: <<insert_date_here>>
Test | State | Date Completed | Tickets | Notes |
OG-CT-1 | Color(green,Pass)? | 2014-09-17 | ||
OG-CT-2 | N/A | No support for bare metal resources | ||
OG-CT-3 | Color(green,Pass)? | 2014-09-10 | ||
OG-CT-4 | N/A | No meso-scale, see OF test (OG-ST-6) in Clemson OpenGENI Stitching Status | ||
OG-CT-5 | Wrong site name and no availability info at GENI monitoring | |||
OG-CT-6 | Color(green,Pass)? | 2014-09-17 | Completed as part of OpenGENI Acceptance testing, see Rack Admin Access test |
Confirmation Tests Logs: Clemson
Request RSpecs: here.
GENI Project Office (GPO)
Overall Site Status:_ <<insert_site_status>>
Confirmation Test Start Date: 2014-08-26
Confirmation Test Completion Date: <<insert_date_here>>
Test | State | Date Completed | Tickets | Notes |
OG-CT-1 | Color(green,Pass)? | 2014-08-26 | ||
OG-CT-2 | N/A | No support for bare metal resources | ||
OG-CT-3 | Color(green,Pass)? | 2014-09-10 | ||
OG-CT-4 | N/A | No meso-scale, see OF test (OG-ST-6) in GPO OpenGENI Stitching Status | ||
OG-CT-5 | Color(#63B8FF,In Progress)? | No availability info at GENI monitoring | ||
OG-CT-6 | Color(green,Pass)? | 2014-09-05 | #1286 |