OG-ADM-3: Full Rack Reboot Test
This page captures status for the test case OG-ADM-3. For additional information see the Acceptance Test Status - May 2013 page overall status, or the OpenGENI Acceptance Test Plan for details about the planned evaluation.
Last Update: 2013/05/20"
Step | State | Notes | Tickets |
Step 1 | Fail | No administrative documentation for shutdown and startup | #83 |
Step 2 | |||
Step 3 |
State Legend | Description |
Pass | Test completed and met all criteria |
Pass: most criteria | Test completed and met most criteria. Exceptions documented |
Fail | Test completed and failed to meet criteria. |
Complete | Test completed but will require re-execution due to expected changes |
Blocked | Blocked by ticketed issue(s). |
In Progress | Currently under test. |
Not Planned | This area is not part of initial evaluation |
Test Plan Steps
Evaluation Notes: No administrative documentation for shutdown and startup. Unable to execute this test case #83.
Step 1. Review relevant documentation
Review relevant rack documentation about shutdown options and make a plan for the order in which to shutdown each component.
Step 2. Shutdown all devices and verify
Cleanly shutdown and/or hard-power-off all devices in the rack, and verify that everything in the rack is powered down.
Step 3. Power on rack and verify health
Power on all devices, bring all logical components back online, and use monitoring and comprehensive health tests to verify that the rack is healthy again.