| 1 | = GR-ADM-1: Rack Receipt and Inventory Test = |
| 2 | |
| 3 | This page captures status for the test case GR-ADM-1. For additional information see the [wiki:GENIRacksHome/GRAMRacks/AcceptanceTestStatusMay2013 Acceptance Test Status - May 2013] page overall status, or the [wiki:GENIRacksHome/AcceptanceTests/GRAMAcceptanceTestsPlan GRAM Acceptance Test Plan] for details about the planned evaluation. |
| 4 | |
| 5 | |
| 6 | ''Last Update: 2013/05/XX" |
| 7 | |
| 8 | || '''Step''' || '''State'''||''' Notes ''' || '''Tickets''' || |
| 9 | || Step 1 ||Not Planned || || || |
| 10 | || Step 2 ||Not Planned || || || |
| 11 | || Step 3 ||Not Planned || || || |
| 12 | || Step 4 ||Not Planned || || || |
| 13 | || Step 5 ||Not Planned || || || |
| 14 | || Step 6 ||Not Planned || || || |
| 15 | |
| 16 | [[BR]] |
| 17 | || '''State Legend''' || '''Description''' || |
| 18 | ||[[span(Pass, style=background-color: green )]] || Test completed and met all criteria || |
| 19 | ||[[span(Pass: most criteria, style=background-color: #98FB98)]]|| Test completed and met most criteria. Exceptions documented || |
| 20 | ||[[span(Fail, style=background-color: red)]] || Test completed and failed to meet criteria. || |
| 21 | ||[[span(Complete, style=background-color: yellow)]] || Test completed but will require re-execution due to expected changes || |
| 22 | ||[[span(Blocked, style=background-color: orange)]] || Blocked by ticketed issue(s). || |
| 23 | ||[[span(In Progress, style=background-color: #63B8FF)]]|| Currently under test. || |
| 24 | ||[[span(Not Planned)]] || This area is not part of initial evaluation || |
| 25 | |
| 26 | |
| 27 | = Test Plan Steps = |
| 28 | |
| 29 | == 1.Power and wire the BBN rack == |
| 30 | |
| 31 | This type of testing is not part of the initial evaluation. |
| 32 | |
| 33 | == 2. Administrator configure GRAM using an administrator account configure the gramm.gpolab.bbn.com DNS namespace and 192.1.242.128/25 IP space, and enters all public IP addresses used by the rack into DNS. == |
| 34 | |
| 35 | This type of testing is not part of the initial evaluation. |
| 36 | |
| 37 | == 3. Administrator requests and receives administrator accounts on the rack and receive read access to all GRAM monitoring of the rack. == |
| 38 | |
| 39 | This type of testing is not part of the initial evaluation. |
| 40 | |
| 41 | == 4. Administrator inventories the physical rack contents, network connections and VLAN configuration, and power connectivity, using standard operational inventories. == |
| 42 | |
| 43 | This type of testing is not part of the initial evaluation. |
| 44 | |
| 45 | == 5 Administrator, GRAM team, and GMOC share information about contact information and change control procedures, and GRAM operators subscribe to GENI operations mailing lists and submit their contact information to GMOC. == |
| 46 | |
| 47 | This type of testing is not part of the initial evaluation. |
| 48 | |
| 49 | == 6. Administrator reviews the documented parts list, power requirements, physical and logical network connectivity requirements, and site administrator community requirements, verifying that these documents should be sufficient for a new site to use when setting up a rack. == |
| 50 | |
| 51 | This type of testing is not part of the initial evaluation. |