This page captures status for the test case OG-EXP-5. For additional information see the Acceptance Test Status - April 2014 page overall status, or the OpenGENI Acceptance Test Plan for details about the planned evaluation.
Scenario | State | Notes | Tickets |
Slice 1: OpenFlow Campus Resource |
State Legend | Description |
Pass | Test completed and met all criteria |
Pass: most criteria | Test completed and met most criteria. Exceptions documented |
Fail | Test completed and failed to meet criteria. |
Complete | Test completed but will require re-execution due to expected changes |
Blocked | Blocked by ticketed issue(s). |
In Progress | Currently under test. |
Test Plan Steps
Test procedure is to be modified, there is no meso-scale connections. Test is simplified to connect these resources in one slice:
- one Clemson campus resource connected to OpenGENI rack switch
- one Clemson rack compute resource
- one InstaGENI rack compute resource.