| 1 | = GR-EXP-5: GRAM Network Resources Acceptance Test = |
| 2 | |
| 3 | This page captures status for the test case GR-EXP-5. For additional information see the [wiki:GENIRacksHome/GRAMRacks/AcceptanceTestStatusApr2014 Acceptance Test Status - April 2014] page overall status, or the [wiki:GENIRacksHome/AcceptanceTests/GRAMAcceptanceTestsPlan GRAM Acceptance Test Plan] for details about the planned evaluation. |
| 4 | |
| 5 | |
| 6 | || '''Scenario''' || '''State''' ||''' Notes ''' || '''Tickets''' || |
| 7 | || Slice 1: !OpenFlow Campus Resource || || || || |
| 8 | [[BR]] |
| 9 | |
| 10 | || '''State Legend''' || '''Description''' || |
| 11 | ||[[span(Pass, style=background-color: green )]] || Test completed and met all criteria || |
| 12 | ||[[span(Pass: most criteria, style=background-color: #98FB98)]]|| Test completed and met most criteria. Exceptions documented || |
| 13 | ||[[span(Fail, style=background-color: red)]] || Test completed and failed to meet criteria. || |
| 14 | ||[[span(Complete, style=background-color: yellow)]] || Test completed but will require re-execution due to expected changes || |
| 15 | ||[[span(Blocked, style=background-color: orange)]] || Blocked by ticketed issue(s). || |
| 16 | ||[[span(In Progress, style=background-color: #63B8FF)]]|| Currently under test. || |
| 17 | |
| 18 | |
| 19 | == Test Plan Steps == |
| 20 | |
| 21 | Test procedure is to be modified, there is no meso-scale connections. Test is simplified to connect these resources in one slice: |
| 22 | - one Clemson campus resource connected to GRAM rack switch |
| 23 | - one Clemson rack compute resource |
| 24 | - one InstaGENI rack compute resource. |
| 25 | |
| 26 | |
| 27 | === Slice 1: !OpenFlow Campus Resource === |
| 28 | |