== InstaGENI Acceptance Tests Open Topic == == Open Topics: 2013-02-27 == === Experimenter Tests === __IG-EXP-7: Click Router Experiment Acceptance Test__ ---> Expected Date: March 01 [[BR]] Niky is modifying click router setup to run in two racks scenario. On 02/26 she was implementing click router environment workarounds. Expect to be able to run test by Friday March 1. === Administrative Tests === __IG-ADM-1: Rack Receipt and Inventory Test__ ---> Expected Date: March 13 Only remaining blocker is government property tags. __IG-ADM-3: Full Rack Reboot Test__ ---> Expected Date: March 11 [[BR]] Need documentation by March 8th, would like to execute on March 11 [[BR]] __IG-ADM-4: Emergency Stop Test__ ---> Expected Date: March 4 (March 5th alternate) [[BR]] An Emergency Stop Procedure detailed test outline is being defined. The preparation steps are currently being executed and coordination is taking place with ES teams. Provided feedback on the InstaGENI documents, which have been addressed. Trying to schedule IG-ADM-4 with the InstaGENI team for March 4th, with the 5th as an alternate or a re-test date. These dates should work for Eldar and the GMOC. There are no blocking issues at this time. __IG-ADM-5: Software Update Test__ ---> Expected Date: March 5 (March 11 alternate) [[BR]] Nick to complete tests the current GENI-recommended versions of FV and FOAM by Friday March 1. Once Nick completes testing and InstaGENI Team requests site admins to upgrade, expect to run upgrade tests on March 4th. If we miss that date, March 11th is the last chance before GEC. __IG-ADM-6: Control Network Disconnection Test__ ---> Expected Date: ??? [[BR]] __IG-ADM-7: Documentation Review Test__ ---> Expected Date: ??? [[BR]] Prioritized outstanding documentation email on 01/31/2013. Waiting on responses. === Monitoring Tests === __IG-MON-1: Control Network Software and VLAN Inspection Test__ ---> Expected Date: ??? [[BR]] __IG-ADM-5: Software Update Test__ ---> Expected Date: ??? [[BR]]