     1== InstaGENI Acceptance Tests Open Topic ==
     2
     3== Open Topics: 2013-02-27 ==
     4
     5=== Experimenter Tests ===   
     6__IG-EXP-7: Click Router Experiment Acceptance Test__   --->   Expected Date: March 01  [[BR]]
     7Niky is modifying click router setup in two racks scenario, On 02/26 she was working on click router environment workarounds.
     8
     9=== Administrative Tests ===
     10_IG-ADM-1: Rack Receipt and Inventory Test__   --->   Expected Date: March 13
     11
     12Only remaining blocker is government property tags.
     13   
     14__IG-ADM-3: Full Rack Reboot Test__  --->   Expected Date: March 11
     15
     16Need documentation by March 8th, would like to execute on March 11.
     17
     18__IG-ADM-4: Emergency Stop Test__   --->   Expected Date: March 4 (March 5th alternate)
     19
     20An Emergency Stop Procedure detailed test outline is being defined.  The preparation steps are currently being executed and soordination is taking place with ES teams. Provided feedback on the InstaGENI documents, which have been addressed. Trying to schedule IG-ADM-4 with the InstaGENI team for March 4th, with the 5th as an alternate or a re-test date. These dates should work for Eldar and the GMOC. There are no blocking issues at this time.
     21
     22
     23__IG-ADM-5: Software Update Test__   --->   Expected Date:  March 5 (March 11 alternate)
     24
     25Nick to complete tests the current GENI-recommended versions of FV and FOAM by Friday March 1.  Once Nick completes testing and InstaGENI Team requests site admins to upgrade, expect to run upgrade tests on March 4th. If we miss that date, March 11th is the last chance before GEC.
     26           
     27__IG-ADM-6: Control Network Disconnection Test__   --->   Expected Date: ???
     28
     29__IG-ADM-7: Documentation Review Test__   --->   Expected Date: ???
     30
     31Prioritized outstanding documentation email on 01/31/2013. Waiting on responses.
     32
     33=== Monitoring Tests ===
     34
     35__IG-MON-1: Control Network Software and VLAN Inspection Test__   --->   Expected Date: ???
     36           
     37__IG-ADM-5: Software Update Test__ --->   Expected Date: ???