Changes between Version 16 and Version 17 of GENIRacksHome/InstageniRacks/AcceptanceTestStatus/IG-ADM-4
- Timestamp:
- 02/26/13 11:37:40 (11 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
GENIRacksHome/InstageniRacks/AcceptanceTestStatus/IG-ADM-4
v16 v17 33 33 = High-level description from test plan = 34 34 35 In this test, an Emergency Stop drill is performed on a sliver in the rack.35 In this test, an Emergency Stop (ES) drill is performed on a sliver in the rack. 36 36 37 37 == Procedure == 38 38 39 * A site administrator reviews the Emergency Stop and sliver shut down procedures, and verifies that these two documents combined fully document the campus side of the Emergency Stopprocedure.40 * A second administrator (or the GPO) submits an E mergency Stoprequest to GMOC, referencing activity from a public IP address assigned to a compute sliver in the rack that is part of the test experiment.41 * GMOC and the first site administrator perform an E mergency Stopdrill in which the site administrator successfully shuts down the sliver in coordination with GMOC.42 * GMOC completes the E mergency Stopworkflow, including updating/closing GMOC tickets.39 * A site administrator reviews the local site ES procedure, GMOC ES procedure, and sliver shut down procedure, and verifies that these documents combined fully document the campus side of the ES procedure. 40 * A second administrator (or the GPO) submits an ES request to GMOC, referencing activity from a public IP address assigned to a compute sliver in the rack that is part of the test experiment. 41 * GMOC and the first site administrator perform an ES drill in which the site administrator successfully shuts down the sliver in coordination with GMOC. 42 * GMOC completes the ES workflow, including updating/closing GMOC tickets. 43 43 44 44 == Criteria to verify as part of this test == … … 49 49 * VII.19. GMOC and a site administrator can perform a successful Emergency Stop drill in which slivers containing compute and OpenFlow-controlled network resources are shut down. (C.3.d) 50 50 51 = Step 1 (prep): Site administrator reviews local site shut down procedure, GMOC shut downprocedure, and InstaGENI sliver shut down procedure =51 = Step 1 (prep): Site administrator reviews local site ES procedure, GMOC ES procedure, and InstaGENI sliver shut down procedure = 52 52 53 The site administrator should review the local site shut down procedure, the E mergency Stopprocedure provided by the GMOC, and the InstaGENI sliver shut down procedure. All of these procedures should make sense together, and the site administrator should follow the local site shut down procedure for the test. The site administrator should identify parts of the local procedure where they need to take action on the aggregate, and they should reference the InstaGENI sliver shut down procedure for that part of the test. He or she should also identify where the local site procedure requires interfacing with another party, such as the GMOC. The parts identified by the site administrator should be verified with the GMOC and with the InstaGENI team.53 The site administrator should review the local site shut down procedure, the ES procedure provided by the GMOC, and the InstaGENI sliver shut down procedure. All of these procedures should make sense together, and the site administrator should follow the local site shut down procedure for the test. The site administrator should identify parts of the local procedure where they need to take action on the aggregate, and they should reference the InstaGENI sliver shut down procedure for that part of the test. He or she should also identify where the local site procedure requires interfacing with another party, such as the GMOC. The parts identified by the site administrator should be verified with the GMOC and with the InstaGENI team. 54 54 55 = Step 2 (prep): GPO, GMOC, and InstaGENI team coordinate a time to run an E mergency Stoptest =55 = Step 2 (prep): GPO, GMOC, and InstaGENI team coordinate a time to run an ES test = 56 56 57 The GPO will coordinate with parties at the GMOC and on the InstaGENI team to identify when an E mergency Stoptest can be run. This test will focus primarily on the interactions with the site administator(s) and performing the procedures documented by the rack team. The following roles will need to be defined for this test:58 * '''GMOC Coordinator''': person from the GMOC who coordinates the E mergency Stopactivity on the GMOC's side57 The GPO will coordinate with parties at the GMOC and on the InstaGENI team to identify when an ES test can be run. This test will focus primarily on the interactions with the site administator(s) and performing the procedures documented by the rack team. The following roles will need to be defined for this test: 58 * '''GMOC Coordinator''': person from the GMOC who coordinates the ES activity on the GMOC's side 59 59 * '''InstaGENI Contact''': person from the InstaGENI team who can be around if there are questions about the document or sliver shut down procedure 60 * '''E mergency StopInitiator''': GPO person who initiates an Emergency Stop request60 * '''ES Initiator''': GPO person who initiates an Emergency Stop request 61 61 * '''Experimenter''': GPO person who has created a sliver 62 62 * '''Site Administrator''': GPO person who is acting as the site administrator of the GPO InstaGENI rack … … 66 66 The experimenter will set up a slice that includes a sliver on the GPO InstaGENI rack. The sliver should be a VM that is attached to the shared mesoscale VLAN, and it should be sending traffic that is visible through monitoring. 67 67 68 = Step 4 (prep): E mergency Stopinitiated =68 = Step 4 (prep): ES initiated = 69 69 70 The E mergency Stop Initiator contacts the GMOC Coordinator to initiate an emergency stoprequest describing the slice name or URN. The GMOC walks quickly walks through their procedure, skipping more formal steps as needed, in order to contact the aggregate operator primary contact.70 The ES Initiator contacts the GMOC Coordinator to initiate an ES request describing the slice name or URN. The GMOC walks quickly walks through their procedure, skipping more formal steps as needed, in order to contact the aggregate operator primary contact. 71 71 72 = Step 5: Site Administrator receives E mergency Stoprequest =72 = Step 5: Site Administrator receives ES request = 73 73 74 74 == Step 5A (verify): Data passed from GMOC to Site Administrator is in expected format ==